Guohua Tongliao Kezuozhongqi Housijing Wind Farm Project
#1318of 1935 in Renewable energy#796of 1084 in China#1044of 1459 in CDM (UNFCCC)#1022of 1287 in ACM0002
Audit Analysis
A CDM wind farm project with VVB-confirmed additionality but significant data quality issues: three corrective action requests (including baseline formula errors), a 47% upward revision of the lifetime ERR between validation and monitoring reports, and contradictory baseline method descriptions. The project's avoidance nature limits permanence risk, but the 0% leakage deduction lacks consistent justification across documents.
Red Flags
- Lifetime ERR revised upward by 47% (from 110,249 in the validation report to 162,118 in the monitoring report), raising over-crediting concerns
- Three corrective action requests at validation, including incorrect formulae and parameters for baseline emissions calculation (CAR 3)
- Baseline method described as 'jurisdictional' in the validation report but 'project' in the monitoring report — a fundamental methodological inconsistency
- Leakage deduction of 0% with justification stated as 'deemed negligible' in the validation report but 'not addressed' in the monitoring report
- No verified ERR figure found in the extracted record; total_err_verified is absent from all available documents
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2014 | 162,118 | 0 | 162,118 | |
| Total | 162,118 | 0 | 162,118 |
Risk Indicators
Combined test, VVB-confirmed
Avoidance project, no reversal risk
0% deduction, inconsistent justification
Method contradictory across documents
Mentioned but FPIC/grievance not detailed
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →