Guohua Tongliao Kezuozhongqi Qiansijing Wind Farm Project

CDM-5713 ↗

#439of 1935 in Renewable energy#172of 1084 in China#284of 1459 in CDM (UNFCCC)#327of 1287 in ACM0002

5.9/ 10
Integrity
7.0
Transparency
5.5
Claim Safety
4.5
Documentation
6.5

Audit Analysis

A CDM wind farm project in China with a confirmed investment-test additionality assessment by ERM and a jurisdictional grid-emission-factor baseline appropriate for the technology. The project delivered approximately 5.9× the pro-rata ex-ante expectation for its first two-year monitoring period, which is a significant over-delivery warranting scrutiny. Multiple parameter contradictions across documents (leakage justification, baseline method, additionality test type) reduce confidence in the internal consistency of the record.

Red Flags

  • Verified emissions reductions of 183,407 tCO₂ for the 2-year monitoring period are approximately 5.9× the pro-rata expectation of ~31,359 tCO₂ derived from the 109,755 tCO₂ ex-ante estimate over the full 7-year crediting period — an extreme over-delivery that requires explanation (capacity ramp-up, grid EF change, or estimation error).
  • Baseline method is described as 'project' in the monitoring report but 'jurisdictional' in the validation report; for a wind project displacing grid electricity, the jurisdictional (grid-average) baseline is the appropriate and expected method, and the inconsistency undermines confidence in the baseline documentation.
  • Leakage justification is stated as 'deemed negligible' in the validation report but 'not addressed' in the monitoring report, creating an inconsistency in how a standard CDM requirement is documented across the project's record.

Credit Vintages

IssuedRetiredAvailable
2014
183,4070183,407
Total183,4070183,407

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Avoidance project, no reversal risk

Leakage

0% deduction, justification inconsistent across docs

Baseline

Jurisdictional grid EF, method contradicted in monitoring re

Safeguards

Safeguards mentioned, FPIC and grievance mechanism not docum

Double-claim

CORSIA and CCP status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-30ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents