Harmanlik Wind Power Plant, Turkey
GS-412 ↗ · current registry ID: GS2544
#71of 1935 in Renewable energy#14of 295 in Turkey#22of 1801 in Gold Standard (GS)#46of 1287 in ACM0002
Audit Analysis
The Harmanlik Wind Power Plant is a Gold Standard wind project with a jurisdictional (grid-emission-factor) baseline, a VVB-confirmed combined additionality test, and no reversal events. The 2024 monitoring period delivered roughly 185% of the pro-rata ex-ante expectation, indicating a conservative baseline. However, the very large volume of corrective actions (40+ items) across the monitoring and verification reports, combined with several cross-document contradictions, tempers confidence in the documentation and transparency of the MRV process.
Red Flags
- 40+ corrective actions were issued across the monitoring and verification reports, many relating to incomplete SDG-impact documentation, missing sustainability monitoring parameters, and administrative inconsistencies in the monitoring report
- A contradiction exists on whether additionality was verified by the VVB: the 2024 verification report confirms it, but the 2025 monitoring report records it as not verified
- The ex-ante lifetime estimate (780,661 tCO2e, 2020 PDD) predates a documented design change for an installed-capacity increase, raising questions about whether the baseline was fully updated
- CORSIA eligibility and CCP status are not stated in any available document, leaving dual-channel risk unassessed
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2015 | 58,862 | 58,862 | 0 | |
| 2016 | 110,088 | 109,571 | 517 | |
| 2017 | 100,088 | 100,088 | 0 | |
| 2018 | 101,431 | 101,418 | 13 | |
| 2019 | 104,881 | 102,393 | 2,488 | |
| 2020 | 106,165 | 3,591 | 102,574 | |
| 2021 | 99,868 | 983 | 98,885 | |
| 2022 | 113,888 | 0 | 113,888 | |
| 2023 | 121,039 | 25,278 | 95,761 | |
| Total | 916,310 | 502,184 | 414,126 |
Risk Indicators
Combined test, VVB-confirmed
Wind – no storage, no reversals
Deemed negligible, 0% deduction
Jurisdictional grid-EF, reassessed 2023
Grievance mechanism present; FPIC not stated
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →