Hasars Landfill Gas Project
#51of 189 in Methane#9of 47 in Mexico#702of 1459 in CDM (UNFCCC)#46of 159 in ACM0001
Audit Analysis
The Hasars Landfill Gas Project (CDM-1240, Mexico) has VVB-confirmed additionality via a combined test and a reasonable 0% leakage deduction for a landfill gas capture project, but suffers from the absence of a buffer pool, several open corrective actions, and material contradictions in baseline characterization and grid emission factor across documents. The project delivered only about 27% of its pro-rata expected emissions reductions for the elapsed monitoring period, which is conservative but raises questions about baseline calibration. Overall, the project is moderately robust with notable data gaps and unresolved monitoring issues.
Red Flags
- No buffer pool or permanence mechanism is stated in any available document, leaving reversal risk unaddressed for a 7-year crediting period
- Three corrective actions remain open (biogas meter specifications, management/emergency plans, local environmental regularization plan) as of the 2011 monitoring report
- The project delivered only ~27% of the pro-rata expected ERR for the elapsed monitoring period (74,704 vs ~275,469 expected), suggesting the PDD baseline may be overestimated
- Grid emission factor contradicts between the monitoring report (0.5036) and an appendix (0.6803), a 35% discrepancy that affects baseline calculations
- Baseline is characterized as 'modeled' in the validation report but 'measured' in the PDD, creating ambiguity about the robustness of the baseline
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2014 | 71,768 | 0 | 71,768 | |
| Total | 71,768 | 0 | 71,768 |
Risk Indicators
VVB-confirmed combined test
mixed evidence / unresolved risk
0% deemed negligible, reasonable for LG
Project-specific, modeled, contradictory
Mentioned but FPIC/grievance not detailed
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.