Hebei Chengde Fengze Wind Farm Project
#310of 1935 in Renewable energy#117of 1084 in China#200of 1459 in CDM (UNFCCC)#231of 1287 in ACM0002
Audit Analysis
A CDM wind project (ACM0002 v08) with VVB-confirmed additionality and a standard jurisdictional grid-emission-factor baseline. The project is fundamentally sound for its type, but data reliability is undermined by contradictions in leakage justification, baseline classification, and claimed ER figures across monitoring reports, and key verification data (verified ERs, FPIC, grievance mechanism) are absent from the extracted record.
Red Flags
- Claimed ER figures differ between two monitoring reports (92,709 in the 2012 report vs 118,643 in the 2011 report), with no explanation for the ~22% discrepancy
- Baseline method is characterised as 'project' in the 2012 monitoring report but 'jurisdictional' in the PDD, creating ambiguity about the baseline basis
- Leakage justification shifts from 'deemed negligible' (validation report, 2009) to 'quantified' (monitoring report, 2012) while the deduction remains 0%, leaving the quantification basis unclear
- No FPIC or grievance mechanism is documented in any available record, despite safeguards being mentioned
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2010 | 60,475 | 0 | 60,475 | |
| 2012 | 118,643 | 0 | 118,643 | |
| 2013 | 92,709 | 0 | 92,709 | |
| Total | 271,827 | 0 | 271,827 |
Risk Indicators
VVB-confirmed combined test
Avoidance project, no reversal risk
Quantified as negligible, 0% deduction
Jurisdictional grid EF, minor doc contradiction
Mentioned but FPIC/grievance not documented
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →