Hebei Shangyi Longyuan Qilinshan Phase II Wind Power Project
#857of 1935 in Renewable energy#446of 1084 in China#611of 1459 in CDM (UNFCCC)#671of 1287 in ACM0002
Audit Analysis
A standard CDM wind power project in China with a well-supported investment additionality test verified by DNV and a jurisdictional grid-emission-factor baseline. However, the available record contains only validation-stage documentation with no monitoring reports or verified emissions reductions, and a significant seven-fold discrepancy in the claimed ERR between the validation report and an appendix raises data-reliability concerns. Safeguards documentation (FPIC, grievance mechanism) is absent from the extracted record.
Red Flags
- Seven-fold discrepancy in total ERR: the validation report (Aug 2012) states 214,807 tCO₂e while an appendix (Jul 2012) states 1,503,649 tCO₂e; the VVB figure is privileged but the unexplained gap undermines confidence in the credit quantity.
- No monitoring reports or verified ERR figures are present in the extracted record, so actual delivery against the claimed 214,807 tCO₂e over the 2012–2019 crediting period cannot be assessed.
- Free, Prior and Informed Consent (FPIC) and a grievance mechanism are not documented in any available source, despite the project being in a populated region of Hebei province.
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
Investment test confirmed by DNV
Avoidance project – no reversal risk
0 % – negligible, appropriate for wind
Jurisdictional grid EF (0.8958, 2012)
Mentioned but FPIC / grievance not documented
CORSIA & CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →