Hefei Longquanshan Landfill Gas Power Generation Project

CDM-2810 ↗

#86of 189 in Methane#749of 1084 in China#988of 1459 in CDM (UNFCCC)#79of 159 in ACM0001

4.8/ 10
Integrity
4.8
Transparency
5.2
Claim Safety
4.3
Documentation
5.2

Audit Analysis

A CDM landfill gas power generation project in China with a VVB-confirmed combined additionality test, but undermined by a direct contradiction on whether gas capture was legally required, a 0% leakage deduction with inconsistent justification across documents, and 14 material findings at validation including calculation errors. The project-specific modeled baseline, absence of a buffer pool, and missing verified performance data limit confidence in the claimed reductions.

Red Flags

  • Contradiction between the PDD (capture legally required = true) and the validation report (capture legally required = false) directly undermines the additionality claim; the VVB's finding is privileged but the discrepancy signals a weak additionality case
  • Leakage deduction of 0% with the PDD stating 'deemed negligible' while the monitoring report records the issue as 'not addressed' — no consistent, quantified leakage treatment across the project lifecycle
  • 14 material findings at validation, including errors in CH4 generation accounting, waste dumping rates, grid emission factors, and IRR calculation, indicating the original PDD contained significant technical inaccuracies
  • No buffer pool percentage stated and no reversal events data available, leaving permanence risk unquantified for a project where gas generation continues after project closure
  • Crediting period discrepancy: the validation report states 2009-10-01 to 2018-09-30 while the later monitoring report states 2010-03-11 to 2020-03-10, a shift of roughly 5 months at both ends

Credit Vintages

IssuedRetiredAvailable
2011
25,395025,395
2012
105,3020105,302
2013
77,025077,025
Total207,7220207,722

Risk Indicators

Additionality

VVB-confirmed but legal-requirement contradiction

Permanence

mixed evidence / unresolved risk

Leakage

0% deduction, inconsistent justification

Baseline

Project-specific, modeled, 2008 grid EF

Safeguards

Mentioned but FPIC and grievance not documented

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-31ACM0001

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents