Henan Jiaozuo Yanxin Cement 4.5+7.5MW WHR Project
#942of 1084 in China#1258of 1459 in CDM (UNFCCC)#15of 28 in ACM0012
Audit Analysis
A CDM waste-heat-recovery project at a cement plant with a confirmed additionality test and no material findings, but severely limited by the absence of any monitoring or verification data, a 10× discrepancy in claimed emissions reductions between the PDD and the validation report, and a low-confidence document extraction. The project's integrity rests on a project-specific baseline and a 2008 grid emission factor, with no evidence of post-validation performance tracking.
Red Flags
- 10× discrepancy in total claimed ERR: the PDD (Apr 2012) states 674,130 tCO₂e while the validation report (Jul 2012) states 67,413 tCO₂e — a factor-of-ten gap that undermines confidence in the credit quantity
- Baseline method contradiction: the validation report classifies the baseline as project-specific, while an appendix references a jurisdictional baseline — the applicable baseline is ambiguous
- No monitoring or verification reports found in the extracted record; the crediting period (2012–2022) has fully elapsed with zero verified performance data
- Low extraction confidence across the document set, indicating at least one key document was poorly readable or incomplete
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed combined test
generation project (lower risk)
Deemed negligible, 0% deduction — reasonable for WHR
Project-specific; method contradicted in appendix; 2008 grid
Safeguards mentioned; benefit-sharing described; FPIC and gr
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →