Henan Xichuan Waste Heat Recovery for Power Generation
#262of 1329 in Industrial#392of 1084 in China#558of 1459 in CDM (UNFCCC)#11of 28 in ACM0004
Audit Analysis
A CDM waste-heat-recovery power project (ACM0004 v2) with VVB-confirmed additionality and a reasonable first-period delivery rate (~89% of pro-rata expectation), but undermined by contradictory leakage justifications, a baseline-method discrepancy between the PDD and monitoring report, and material findings that QA/QC procedures were not implemented as described. The project is an avoidance-type EE credit with low inherent permanence risk, yet the absence of a stated buffer pool and the unresolved documentation gaps limit confidence.
Red Flags
- Leakage justification is contradictory: the validation report (2008) states leakage was 'deemed negligible' while the monitoring report (2010) records it as 'not addressed', and the deduction is 0% in both cases
- QA/QC procedures for regular testing and maintenance were not implemented as described in the PDD, per the monitoring report's material findings
- Baseline method is characterised as 'project' in the monitoring report but 'jurisdictional' in the PDD, creating ambiguity about the reference scenario
- Equipment capacity decreased from 9 MW to 7.5 MW during the monitoring period, and the monitoring parameter EGgrid-in had to be replaced by EGoutput because no power transaction occurred
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2011 | 38,086 | 0 | 38,086 | |
| Total | 38,086 | 0 | 38,086 |
Risk Indicators
VVB-confirmed combined test
EE avoidance, no reversal risk
0% deduction, contradictory justification
Method contradictory across docs
Mentioned but FPIC/grievance not stated
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →