Hongba Small Hydropower Project in Gansu Province

CDM-3864 ↗

#866of 1935 in Renewable energy#456of 1084 in China#620of 1459 in CDM (UNFCCC)#286of 806 in AMS-I.D

5.3/ 10
Integrity
5.2
Transparency
5.5
Claim Safety
5.0
Documentation
5.5

Audit Analysis

The Hongba Small Hydropower Project is a straightforward grid-connected renewable electricity project under CDM with a confirmed investment-test additionality assessment by Applus+ LGAI. However, the project carries a notable burden of ten material findings and six corrective actions, and the available documents contain four contradictions — including a fundamental disagreement on whether the baseline is project-specific or jurisdictional — that undermine confidence in the credit quantity. The absence of a buffer pool, verified ERR figures, and any permanence or safeguards detail leaves meaningful gaps in the evidence base.

Red Flags

  • Baseline method is stated as 'project' in the 2013 monitoring report but 'jurisdictional' in the 2010 PDD — a fundamental disagreement on the credit-quantity foundation
  • Ten material findings (six corrective actions, four comments) were raised by the VVB, including the need to revise the crediting-period start date, recalculate the carbon model with newer data, and justify that the project is not a debundled activity
  • Leakage justification is contradictory: the 2010 validation report calls it 'deemed negligible' while the 2013 monitoring report calls it 'quantified', yet both arrive at a 0% deduction with no visible quantification in the extracted record
  • No buffer pool percentage, no reversal-event history, and no permanence mechanism are stated in any available document, leaving the permanence risk for a dam-based project unaddressed

Credit Vintages

IssuedRetiredAvailable
2012
19,706019,706
2014
34,085034,085
Total53,791053,791

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

mixed evidence / unresolved risk

Leakage

0% deduction, contradictory justifications

Baseline

Project vs jurisdictional contradiction

Safeguards

Mentioned but FPIC and grievance not detailed

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-31AMS-I.D. Grid connected renewable electricity generation

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents