Honiton Energy Bailingmiao Phase Two Windfarm Project
GS-893 ↗ · current registry ID: GS505
#394of 1084 in China#439of 1801 in Gold Standard (GS)#609of 1287 in ACM0002
Audit Analysis
A Gold Standard wind project in China with VVB-verified additionality and no inherent reversal risk, but hampered by a project-specific baseline, a 0% leakage deduction with contradictory justifications across documents, and a notably high volume of corrective and clarification requests (8 CARs, 6 CLs) that signal MRV data-quality weaknesses. The most recent one-month monitoring period delivered only about 32% of the pro-rata ex-ante expectation, though this is within the range of normal wind variability given the prior period's over-delivery.
Red Flags
- Eight corrective action requests and six clarification requests were raised and closed during verification, including missing meter calibration records, missing original electricity data for Jan–Feb 2012, and spreadsheet data-linkage errors — indicating recurring MRV quality issues.
- The most recent monitoring period (Aug–Sep 2016, one month) verified only 3,149 tCO2e against a pro-rata expectation of roughly 9,717 tCO2e (≈32%), a significant short-term under-delivery that warrants scrutiny of capacity-factor assumptions.
- Leakage justification is contradictory: the verification report (2017) states leakage was 'quantified' while the monitoring report (2015) states it was 'deemed negligible,' yet the deduction is 0% in both cases.
- Grid emission factor differs between the PDD (1.0548, 2009) and the verification report (0.9502), a 10% swing that affects credit volume; the lower value used in verification is conservative but the basis for the change is not clearly documented.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2011 | 33,562 | 26,510 | 7,052 | |
| 2013 | 2,746 | 0 | 2,746 | |
| 2014 | 102,358 | 89,797 | 12,561 | |
| 2015 | 62,206 | 46,745 | 15,461 | |
| 2016 | 3,149 | 2,993 | 156 | |
| Total | 204,021 | 166,045 | 37,976 |
Risk Indicators
VVB-verified combined test
Avoidance project, no reversal risk
0% deduction, contradictory justification
Project-specific, no reassessment date
FPIC and benefit sharing noted, grievance mechanism not stated
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →