Huadian Inner Mongolia Guyang Hongnijing Wind Farm Project
#781of 1935 in Renewable energy#396of 1084 in China#561of 1459 in CDM (UNFCCC)#611of 1287 in ACM0002
Audit Analysis
A CDM wind farm project in Inner Mongolia with a confirmed additionality assessment by TÜV NORD CERT and a reasonable grid emission factor, but undermined by 13 material findings at validation (all subsequently resolved) and a notable contradiction in the stated baseline methodology between the validation and monitoring reports. The project delivered approximately 95% of its pro-rata ex-ante expectation for the first monitoring period, indicating modest but credible performance.
Red Flags
- 13 material findings were raised at validation, including missing approval letters, missing generator technical parameters, an outdated emission-factor calculation tool, and inconsistencies between the PDD meter description and the actual installation
- Baseline methodology is stated as 'project' in the monitoring report but 'jurisdictional' in the validation report — an unresolved contradiction that affects the credibility of the baseline
- Verified ERR figure is not stated in the extracted record, preventing independent confirmation of the claimed 75,739 tCO₂e for the first monitoring period
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2013 | 75,737 | 0 | 75,737 | |
| Total | 75,737 | 0 | 75,737 |
Risk Indicators
VVB-confirmed combined test
Wind generation, no reversal risk
0% deduction, justified for wind
Method contradiction across documents
Mentioned but FPIC/grievance not detailed
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →