Audit Analysis
A VCS-registered solar milling project in Zambia with VVB-verified additionality and low inherent reversal risk, but significant documentation weaknesses including nine material findings at validation, no verified emission reduction data, assumed (not measured) usage rates, and a project-specific baseline. The low extraction confidence and absence of any monitoring-period data limit confidence in the project's ongoing performance.
Red Flags
- No verified emission reduction figure is available in any document; only the lifetime claimed total of 150,710 tCO2e is recorded, making over- or under-delivery impossible to assess
- Nine material findings and eleven corrective actions were raised at validation, including missing commissioning dates, incomplete stakeholder consultation records, and a methodology switch from AMS-I.F to AMS-I.B that required re-justification
- Usage rate of 6 (presumed hours/day) is assumed rather than measured, and the monitoring method is described as 'assumed' in the validation report, creating a gap between claimed and actual energy displacement
- Minimum extraction confidence is rated low, indicating at least one key document was poorly readable, which undermines confidence in the extracted data set
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-verified barrier test
Avoidance project, no reversal risk
0% deduction, qualitative justification only
Project-specific, no reassessment date recorded
FPIC and grievance mechanism documented
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →