Juruá REDD+ Project
#45of 261 in Soil carbon#54of 211 in Brazil#467of 1339 in Verra (VCS)#7of 29 in VM0015
Audit Analysis
The Juruá REDD+ Project is a VCS-registered avoidance project in Brazil with a VVB-verified investment additionality test, an 11% buffer pool, and a 10% quantified leakage deduction. However, the verification report records 29 clarification requests and 25 corrective actions, a sampling error that initially exceeded the 5% materiality threshold, and a resolved overlap with the Valparaiso project, all of which raise data-reliability concerns. The lifetime ERR estimate was revised downward by roughly 79% between the PDD and the validation report, and the first monitoring period delivered only about 11% of the pro-rata expectation derived from the original PDD figure.
Red Flags
- 29 clarification requests and 25 corrective actions raised during verification, including sampling error above the 5% materiality threshold and data inconsistencies between PD/MR tables and calculation spreadsheets
- Overlap with the Valparaiso VCS project was identified, creating a double-counting risk that required a Verra response to resolve
- Lifetime ERR estimate dropped from 1,937,742 tCO₂e (PDD, 2022) to 413,927 tCO₂e (validation report, 2025), a 79% reduction that undermines confidence in the original ex-ante modelling
- Reversal-events field is contradictory: the verification report (Aug 2025) marks it as 'not addressed' while the validation report (Jun 2025) states 'none reported'; the detail field indicates the AFOLU Non-Permanence Risk Tool was applied but the top-level field was left unresolved
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test
11% buffer, no reversals, but field unresolved
10% quantified deduction
Project-specific; reassessment not yet due
FPIC, grievance mechanism, safeguards documented
CORSIA/CCP not stated; Valparaiso overlap resolved
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.