Lingbi County Wastewater Treatment Plant Project
#20of 108 in Water#233of 1084 in China#277of 1339 in Verra (VCS)#1of 6 in AM0080
Audit Analysis
The Lingbi County Wastewater Treatment Plant project has a solid additionality foundation confirmed by a well-known VVB and low inherent permanence risk, but is undermined by a project-specific modeled baseline, five material findings (including parameter errors and a 17.65% under-delivery), and multiple cross-document contradictions. The project is under-delivering relative to its ex-ante estimate, which limits over-crediting risk but raises questions about the robustness of the original calculations.
Red Flags
- Five material findings in the verification report, including incorrect parameter source values (CODBL,WW,y, CODPJ,WW,y, ADBL) and a CH4/CO2 misidentification in the major emission sources table, indicating calculation and reporting errors that required corrective actions.
- The actual emission reduction is 17.65% lower than the registered PDD estimate, attributed to lower influent flow/COD and higher electricity consumption, suggesting the ex-ante assumptions were optimistic.
- Six contradictions across documents, including conflicting ERR figures (95,511 vs 76,591) within the same monitoring report, conflicting additionality test descriptions (investment vs combined), and conflicting FPIC and benefit-sharing statements.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2020 | 52,963 | 52,963 | 0 | |
| 2021 | 51,484 | 51,484 | 0 | |
| 2022 | 55,289 | 55,262 | 27 | |
| 2023 | 53,178 | 40,184 | 12,994 | |
| 2024 | 54,567 | 0 | 54,567 | |
| Total | 267,481 | 199,893 | 67,588 |
Risk Indicators
VVB-confirmed investment/combined test
Avoidance project; non-permanence N/A
0% deduction, 'deemed negligible' only
Project-specific, modeled; not yet due for reassessment
FPIC conducted, grievance mechanism present
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →