Audit Analysis
The Moelven Limtre project is a Norwegian timber-construction alternative-materials credit verified by DNV, with a 10% buffer pool and no material findings. However, the additionality rests on a weak 'common practice' test, leakage is entirely unaddressed despite being a material pathway for displaced concrete/steel production, and the project is CORSIA-eligible creating dual-channel risk. The absence of an ex-ante lifetime estimate and several MRV parameters limits confidence in the credit's robustness.
Red Flags
- Leakage deduction and justification are both absent from the record — for an alternative-materials project displacing concrete or steel, the continued production of those materials elsewhere is a material leakage pathway that has not been quantified or dismissed.
- CORSIA eligibility is confirmed while CCP status is not stated, creating potential dual-channel allocation risk.
- Additionality is established solely via a 'common practice' test, which is a weaker basis than an investment or regulatory test, particularly in Norway where timber construction is well established.
Credit Vintages Exhausted
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2021 | 2,269 | 2,269 | 0 | |
| 2022 | 3,657 | 3,657 | 0 | |
| Total | 5,926 | 5,926 | 0 |
Risk Indicators
Common-practice test, VVB-verified but weak basis
mixed evidence / unresolved risk
No deduction or justification stated
Project-specific, no reassessment date
Mentioned but FPIC and grievance mechanism not confirmed
CORSIA-eligible, CCP status not stated
Where to buy
Marketplaces
+ Know where to buy this?
Listing multiple projects? Send us a CSV at [email protected].
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →