Mudurnu Biogas Energy Power Plant
#174of 268 in Biogas#260of 295 in Turkey#1009of 1339 in Verra (VCS)#14of 20 in AM0073
Audit Analysis
The Mudurnu Biogas Energy Power Plant is a VCS-registered manure-to-biogas project in Turkey with a confirmed combined additionality test and no inherent reversal risk, but the extracted record contains no monitoring or verification data whatsoever, leaving the 634,894-tonne lifetime claim entirely unverified. The 0% leakage deduction rests on a thin 'quantified' justification, and the absence of CORSIA/CCP status information prevents ruling out dual-channel risk. Overall, the project's design is sound but the evidence base is too sparse to confirm delivery.
Red Flags
- No monitoring report or verified ERR figure found in any available document despite the crediting period running since February 2021
- Leakage deduction of 0% justified only as 'quantified' with no further detail in a manure-treatment project where untreated waste at collection sites is a plausible leakage pathway
- CORSIA eligibility and CCP status are both unstated, leaving dual-channel crediting risk unassessed
- Low extraction confidence indicates at least one key document was poorly readable, reducing reliability of the extracted record
- A Forward Action Request noted the absence of a flow meter for biogas routed to flare, an MRV gap that could affect emission accounting accuracy
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
Combined test, VVB-confirmed
Non-AFOLU, no reversal risk
0% deduction, thin justification
Project-specific, modelled, no reassessment date
Grievance mechanism present, FPIC not conducted
CORSIA and CCP status both unstated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →