VCSEnergy industries (renewable/non-renewable sources)Namibia Registry: RegisteredAMS-I.D

Outapi Pv Plant

VCS-1766 ↗

#275of 1935 in Renewable energy#1of 8 in Namibia#128of 1339 in Verra (VCS)#99of 806 in AMS-I.D

6.2/ 10
Integrity
6.5
Transparency
6.0
Claim Safety
6.5
Documentation
5.5

Audit Analysis

The Outapi PV Plant is a standard VCS renewable energy project with a well-established investment-test additionality confirmed by the VVB and a jurisdictional grid-emission-factor baseline. However, three Corrective Action Requests during verification—including reliance on a check meter due to missing main-meter calibration proof, inclusion of pre-crediting-period generation, and an internal inconsistency in the grid emission factor—introduce moderate data-quality concerns that temper an otherwise conventional credit profile.

Red Flags

  • Calibration proof for the main meter could not be provided; generation data for the 2023–2025 verification relied solely on a check meter (verification report, 2025-10-07).
  • Net power generation included output from June 2018, before the official crediting-period start of 1 July 2018 (corrective action in verification report).
  • The grid emission factor applied in the monitoring report was inconsistent with the value used in the supporting Excel workbook (corrective action in verification report).
  • Leakage justification is inconsistent across documents: the 2022 verification report records it as 'not addressed' while the 2025 monitoring report states 'deemed negligible'—no quantitative leakage analysis is present in either.

Credit Vintages

IssuedRetiredAvailable
2018
3,7733,7730
2019
4,4364,4360
2020
7,6787,6780
2021
10,00610,0060
2022
11,1405,6465,494
2023
10,797010,797
2024
11,363011,363
2025
2,51102,511
Total61,70431,53930,165

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Generation project, no reversal risk

Leakage

0% deduction, justification inconsistent across docs

Baseline

Jurisdictional grid EF, standard method

Safeguards

FPIC, grievance mechanism, safeguards documented

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-03AMS-I.D

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.