Ozaltın Otel Solar Power Plant
#1044of 1935 in Renewable energy#16of 75 in TR#31of 154 in Intl. Carbon Registry (ICR)#824of 1287 in ACM0002
Audit Analysis
The Ozaltın Otel Solar Power Plant is a grid-connected solar project in Turkey using a jurisdictional baseline with a 2024 grid emission factor of 0.6261 tCO₂/MWh. The project type carries inherently low permanence and leakage risk, and safeguards documentation (FPIC, grievance mechanism, benefit sharing) is present. However, the absence of a confirmed VVB verification, lack of any monitoring data, and low document extraction confidence limit confidence in the overall assessment.
Red Flags
- Additionality test type is stated as 'combined' but no VVB verification of additionality is confirmed in the available documents; the VVB name is not identified
- No monitoring period data or verified ERR figures are available; the project has no independent verification of actual performance
- Minimum extraction confidence is rated 'low', indicating at least one key document was poorly readable, reducing reliability of the extracted record
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2024 | 43,003 | 0 | 43,003 | |
| 2025 | 57,335 | 0 | 57,335 | |
| 2026 | 62,296 | 0 | 62,296 | |
| 2027 | 62,296 | 0 | 62,296 | |
| 2028 | 62,296 | 0 | 62,296 | |
| 2029 | 62,296 | 0 | 62,296 | |
| 2030 | 62,296 | 0 | 62,296 | |
| 2031 | 62,296 | 0 | 62,296 | |
| 2032 | 62,296 | 0 | 62,296 | |
| 2033 | 62,296 | 0 | 62,296 | |
| 2034 | 12,459 | 0 | 12,459 | |
| Total | 611,165 | 0 | 611,165 |
Risk Indicators
Combined test stated but VVB verification unconfirmed
Avoidance project, no reversal risk
0% with negligible justification, appropriate for solar
Jurisdictional baseline, 2024 grid EF
FPIC, grievance mechanism, benefit sharing documented
CCP and CORSIA status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →