PANAB TEKIRDAG BIOGAS PLANT
GS-3215 ↗ · current registry ID: GS11226
#43of 268 in Biogas#160of 295 in Turkey#451of 1801 in Gold Standard (GS)#35of 159 in ACM0001
Audit Analysis
The Panab Tekirdağ Biogas Plant is a Gold Standard biogas-to-electricity project with a verified investment additionality test and no reported reversal events, but its integrity is undermined by a contradictory leakage treatment (0% deduction with conflicting justifications across documents), the absence of FPIC, and an unquantified buffer pool. Transparency is moderate: the VVB is identified and claimed/verified ERR figures match exactly, yet several key MRV parameters (FNRB method, usage monitoring, CORSIA/CCP status) are not stated in the available record.
Red Flags
- Leakage justification is contradictory: the verification report (Dec 2025) states leakage was 'quantified' while the monitoring report (Dec 2025) states it was 'not addressed'; the 0% deduction lacks a clear, consistent basis.
- FPIC was not conducted despite the project's presence in a community context in Turkey.
- One Forward Action Request remains open regarding the investment analysis if plant capacity exceeds 10 MW, indicating an unresolved additionality boundary question.
- CORSIA eligibility and CCP status are both unstated, leaving dual-channel crediting risk unassessed.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2022 | 188,840 | 0 | 188,840 | |
| 2023 | 200,448 | 0 | 200,448 | |
| 2024 | 6,618 | 0 | 6,618 | |
| Total | 395,906 | 0 | 395,906 |
Risk Indicators
VVB-confirmed investment test
mixed evidence / unresolved risk
0% deduction, contradictory justification
Project-specific, modeled, no reassessment date
Grievance & benefit sharing present, FPIC absent
CORSIA and CCP status both unstated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →