Permanent Abandonment of Marginal Oil and Natural Gas Wells
#57of 189 in Methane#160of 345 in United States#32of 154 in Intl. Carbon Registry (ICR)
Audit Analysis
A permanent well-abandonment methane avoidance project with a fundamentally sound design (no reversal risk, VVB-confirmed additionality, 5% buffer pool), but undermined by significant data-reliability issues including a three-fold discrepancy in the lifetime ex-ante estimate between the PDD and the validation report, a project-specific baseline, and an extensive list of initial documentation deficiencies (9 CARs, 11 CLs) that were subsequently resolved. The verified monitoring-period figure aligns closely with the PDD's pro-rata expectation, but the unresolved contradiction in the lifetime figure casts a shadow over the overall credit volume.
Red Flags
- Lifetime ex-ante estimate differs by a factor of ~3 between the PDD (220,205 tCO2e) and the validation report (652,874 tCO2e), creating material uncertainty about the true credit volume
- A calculation error in baseline emissions was identified during validation and corrected, and project emissions from diesel/transport were initially omitted before being included in the final quantification
- Leakage justification is internally inconsistent within the validation report: described as 'quantified' in one section (2025-10-01) and 'deemed negligible' in another (2025-09-16), while the applied deduction is 0%
- Stakeholder consultation was limited to landowner agreements; formal community outreach was not conducted, and the ongoing consultation plan lacked a clear schedule
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2024 | 723 | 0 | 723 | |
| 2025 | 22,020 | 0 | 22,020 | |
| 2026 | 22,021 | 0 | 22,021 | |
| 2027 | 22,020 | 0 | 22,020 | |
| 2028 | 22,021 | 0 | 22,021 | |
| 2029 | 22,020 | 0 | 22,020 | |
| 2030 | 22,021 | 0 | 22,021 | |
| 2031 | 22,020 | 0 | 22,020 | |
| 2032 | 22,021 | 0 | 22,021 | |
| 2033 | 22,020 | 0 | 22,020 | |
| 2034 | 21,298 | 0 | 21,298 | |
| Total | 220,205 | 0 | 220,205 |
Risk Indicators
VVB-confirmed investment test
mixed evidence / unresolved risk
0% deduction reasonable for permanent abandonment
Project-specific measured baseline, ex-ante figure disputed
Grievance mechanism present, FPIC not conducted, limited community outreach
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →