Pingyuan Landfill Gas Power Generation Phase I Project
#153of 189 in Methane#999of 1084 in China#1146of 1339 in Verra (VCS)#130of 159 in ACM0001
Audit Analysis
The Pingyuan Landfill Gas Power Generation project is a VCS-registered LFG-to-energy project verified by Applus+ with an investment-test additionality assessment confirmed by the VVB. However, the verification report lists seven material findings and nine corrective actions, and a critical contradiction exists over whether landfill gas capture is legally required (true in the monitoring report, false in the validation report), which directly undermines the additionality claim. The project delivered roughly 80% of its pro-rata ex-ante expectation for the elapsed monitoring period, which is conservative, but a 58% discrepancy in the grid emission factor between the monitoring and verification reports raises over-crediting concerns.
Red Flags
- Contradiction on whether LFG capture is legally required: the monitoring report (2024) states true while the validation report (2023) states false — if capture is legally mandated, additionality is fundamentally undermined
- Grid emission factor discrepancy of 58% between the monitoring report (0.50885) and the verification report (0.8042), which directly affects the magnitude of claimed credits
- Seven material findings and nine corrective actions in the verification report, including baseline calculation errors (CH4 flaring status, FCH4 values, landfill volume) and unclear LFG treatment/emergency procedures
- Baseline described as 'measured' in the monitoring report but 'modeled' in the PDD, creating uncertainty about baseline robustness
- Gas capture legally mandated — additionality in doubt
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2021 | 10,000 | 9,511 | 489 | |
| 2022 | 40,509 | 40,509 | 0 | |
| 2023 | 13,382 | 2,650 | 10,732 | |
| Total | 63,891 | 52,670 | 11,221 |
Risk Indicators
VVB-confirmed but capture-requirement contradiction unresolved
mixed evidence / unresolved risk
Quantified at 0% with justification (LFG context)
Project-specific; measured vs modeled contradiction; not yet due for reassessment
FPIC and grievance mechanism present, but stakeholder consultation flagged as insufficient
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →