'Posco Uruguay' afforestation on degraded extensive grazing land
#11of 80 in ARR (afforestation)#6of 15 in Uruguay#629of 1459 in CDM (UNFCCC)#2of 8 in AR-ACM0001
Audit Analysis
The Posco Uruguay afforestation project demonstrates solid additionality through a combined test confirmed by Bureau Veritas Brasil, and uses the CDM's lCER mechanism to address non-permanence risk. However, the project-specific baseline, a 0% leakage deduction justified only as 'deemed negligible,' and the complete absence of monitoring or verified ERR data in the available record limit confidence in the claimed 658.7 tCO₂e reductions. The documentation is confined to validation-era (2010) sources with low extraction confidence, leaving a significant evidence gap for a project whose crediting period runs to 2039.
Red Flags
- No monitoring reports or verified ERR figures are present in the extracted record; the only ERR figure (658.714 tCO₂e) is a claimed value with no independent verification available
- Leakage deduction is 0% with justification limited to 'deemed negligible' — no quantitative analysis or scenario comparison is documented
- FPIC was not conducted; while the validation report resolved this by confirming no indigenous communities in the project area (CAR 09), the absence of a formal FPIC process is a safeguard gap
- Minimum extraction confidence is rated 'low,' indicating at least one key document was poorly readable, reducing reliability of the extracted data
- Buffer pool size not disclosed in available documents
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
Combined test, VVB-confirmed
lCER mechanism, no buffer pool
0% deduction, minimal justification
Project-specific, set 2009
Grievance & benefit sharing present, no FPIC
CORSIA/CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →