Regenerative Agriculture with small holder farming communities of Bangladesh
#168of 261 in Soil carbon#112of 121 in Bangladesh#1077of 1339 in Verra (VCS)#5of 8 in VM0017
Audit Analysis
A VCS ALM soil-carbon project in Bangladesh with VVB-confirmed additionality and a 28% buffer pool, but undermined by a 4.8× discrepancy between the PDD and validation report on lifetime ERR, a 0% leakage deduction with no justification in the most recent validation report, and three open forward action requests. The absence of any verified ERR figure and low extraction confidence across 12 documented contradictions make it difficult to confirm that claimed credits are safely supported.
Red Flags
- Lifetime ERR differs by a factor of ~4.8 between the PDD (1,840,000 tCO₂e) and the validation report (381,928 tCO₂e); the PDD figure may have been used for initial registration
- Leakage deduction is 0% and the most recent validation report (Dec 2025) records the justification as 'not addressed', while the earlier validation report (Mar 2024) stated 'deemed negligible' — no quantitative leakage analysis is on file
- Buffer pool percentage is 28% in the PDD but 16.25% in an appendix; the applicable VCS requirement for VM0017 is not clearly reconciled
- Three Forward Action Requests remain open at validation, including establishing a clear benefit-sharing mechanism and documenting individual farmer land holdings
- No verified ERR figure is available for the 2022–2024 monitoring period, so actual delivery cannot be assessed against the pro-rata expectation
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed barrier test
28% buffer pool; no reversals; pool % disputed
0% deduction, justification not addressed
Project-specific, mixed; reassessment not yet due
FPIC & grievance per VVB; appendix contradicts; FAR open
CORSIA & CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →