Audit Analysis
The Renoe Acipayam Solar Power Plant is a Gold Standard solar thermal project in Turkey with a VVB-verified combined additionality test and a project-specific baseline reassessed in 2023. However, the project carries significant data-reliability concerns: 40+ corrective actions were required before issuance, multiple ERR figures contradict across monitoring and verification reports, and no buffer pool percentage is stated. The first monitoring period shows a 352% over-delivery relative to the pro-rata ex-ante expectation, which, while potentially explainable by seasonal solar peaks, warrants scrutiny given the surrounding data inconsistencies.
Red Flags
- 40+ corrective actions and 24 CARs were required before credit issuance, indicating substantial documentation and calculation quality issues in both the PDD and Monitoring Report
- Two monitoring reports (Feb 2025 and Nov 2025) report claimed ERRs of 19,007 and 4,391 tCO2e respectively — a 4.3× discrepancy that, even if attributable to different periods, signals data-management weakness
- Baseline method is contradictory: the 2024 verification report describes a project-specific baseline while the 2023 verification report references a jurisdictional baseline
- Verified ERR of 19,007 tCO2e for a 5-month period is 352% of the pro-rata ex-ante expectation (5,407 tCO2e), raising questions about the conservatism of the ex-ante estimate or the accuracy of the monitoring calculation
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2018 | 9,596 | 9,488 | 108 | |
| 2019 | 10,065 | 3,701 | 6,364 | |
| 2020 | 10,375 | 207 | 10,168 | |
| 2021 | 10,334 | 206 | 10,128 | |
| 2022 | 10,110 | 0 | 10,110 | |
| 2023 | 11,398 | 0 | 11,398 | |
| 2024 | 7,609 | 0 | 7,609 | |
| Total | 69,487 | 13,602 | 55,885 |
Risk Indicators
VVB-verified combined test
low inherent reversal risk
0% deduction; justification contradicts PDD
Project-specific; method contradictory across VRs
Grievance mechanism and benefit sharing present; FPIC not stated
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →