Shandan Dongle Beitan 50MW Solar Power Generation Project
#886of 1935 in Renewable energy#465of 1084 in China#553of 1339 in Verra (VCS)#699of 1287 in ACM0002
Audit Analysis
A 50 MW grid-connected solar project under VCS ACM0002 with a solid additionality assessment (combined test, VVB-verified) and reasonable leakage treatment, but undermined by 11 material findings, a baseline-method contradiction between documents, and low extraction confidence across the 20-document record. The ERR figures are internally consistent (claimed equals verified at 213,469 tCO₂e over the full 10-year crediting period), and permanence risk is not applicable for a renewable-energy project.
Red Flags
- Eleven material findings in the 2024 verification report, including crediting-period inconsistency, missing IRR sensitivity analysis, and incorrect methodology naming, all requiring corrective action
- Baseline method described as 'project' in the 2020 verification report but 'jurisdictional' in the 2024 monitoring report — an unresolved contradiction that affects baseline credibility
- Minimum extraction confidence rated low, meaning at least one key document was poorly readable and the structured record may be incomplete
- CORSIA eligibility and CCP status are not stated in any available document, leaving dual-channel risk unassessed
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2013 | 48,393 | 48,393 | 0 | |
| 2014 | 46,825 | 46,825 | 0 | |
| 2015 | 93,384 | 93,384 | 0 | |
| 2016 | 102,400 | 102,400 | 0 | |
| 2017 | 61,623 | 53,277 | 8,346 | |
| 2018 | 55,546 | 55,546 | 0 | |
| 2020 | 36,429 | 13,665 | 22,764 | |
| 2021 | 68,148 | 68,148 | 0 | |
| 2022 | 69,025 | 63,424 | 5,601 | |
| 2023 | 66,594 | 216 | 66,378 | |
| Total | 648,367 | 545,278 | 103,089 |
Risk Indicators
Combined test, VVB-verified
N/A – renewable energy, no storage
0 % – negligible, justified
Project-specific; method contradiction across docs
FPIC, grievance mechanism, safeguards documented
CORSIA & CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →