Soc Son Waste to Power Plant Project
#35of 80 in Vietnam#422of 1339 in Verra (VCS)#5of 31 in ACM0022
Audit Analysis
The Soc Son Waste-to-Power project is a VCS-registered avoidance project with VVB-confirmed additionality and no permanence risk, but it suffers from a thin leakage justification (0% deemed negligible), a project-specific baseline with a 2019 grid emission factor, and a complete absence of verified monitoring data. Low extraction confidence and the lack of any monitoring report in the evidence base limit confidence in the project's ongoing performance.
Red Flags
- Leakage deduction of 0% justified only as 'deemed negligible' without quantified analysis, which is weak for a waste-to-energy project where displaced waste or displaced electricity could create leakage pathways
- No verified ERR data available (no monitoring report in evidence), making it impossible to assess whether the project is delivering on its claimed 3.81 MtCO2e over the crediting period
- Low extraction confidence across the document set, indicating at least one key document was poorly readable or incomplete
- Four material findings (CARs) at validation related to stakeholder consultation, EIA justification, public comment period, and methodology applicability — all resolved but indicating initial documentation gaps
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed combined test
Avoidance project, no reversal risk
0% deduction, thin justification
Project-specific, 2019 grid EF
Grievance & benefit sharing present, FPIC not stated
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →