*Suzhou Qizi Mountain Landfill Gas Recovery Project (300259)
GS-1643 ↗ · current registry ID: GS397
#94of 189 in Methane#781of 1084 in China#1130of 1801 in Gold Standard (GS)#87of 159 in ACM0001
Audit Analysis
The Suzhou Qizi Mountain Landfill Gas Recovery Project has a confirmed additionality assessment and a named VVB, but is undermined by three corrective action requests (meter calibration error, non-ideal ER calculation method, and inconsistent emission values), a 0% leakage deduction with contradictory justification, and no buffer pool or reversal-risk treatment. CCP approval introduces dual-channel risk, and several key MRV parameters (FNRB method, usage monitoring, CORSIA eligibility) are absent from the extracted record.
Red Flags
- Three Corrective Action Requests raised by the VVB: meter FD21246A calibration mismatch, ER calculation not based on directly monitored LFG parameters, and emission reduction values inconsistent with the calculation spreadsheet
- Leakage deduction of 0% with justification described as 'not addressed' in the verification report, contradicting the validation report's 'deemed negligible' claim
- Reversal events explicitly 'not addressed' and no buffer pool percentage stated, leaving permanence risk unquantified for a landfill gas project
- CCP status is 'approved', creating dual-channel risk with China's domestic carbon market while CORSIA eligibility is not stated
- FPIC recorded as not conducted in the validation report (2021), contradicting a 2017 appendix that records it as conducted
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2007 | 63,963 | 62,929 | 1,034 | |
| 2008 | 85,341 | 73,614 | 11,727 | |
| 2009 | 97,707 | 97,706 | 1 | |
| 2010 | 123,454 | 120,880 | 2,574 | |
| 2011 | 106,637 | 96,991 | 9,646 | |
| 2012 | 84,477 | 84,477 | 0 | |
| 2013 | 96,039 | 96,039 | 0 | |
| 2014 | 129,224 | 122,337 | 6,887 | |
| 2015 | 104,000 | 104,000 | 0 | |
| 2016 | 120,694 | 110,694 | 10,000 | |
| 2017 | 112,075 | 107,075 | 5,000 | |
| 2018 | 144,201 | 144,201 | 0 | |
| 2019 | 135,328 | 93,078 | 42,250 | |
| 2020 | 133,714 | 117,947 | 15,767 | |
| 2021 | 46,186 | 46,186 | 0 | |
| 2022 | 5,258 | 5,258 | 0 | |
| Total | 1,588,298 | 1,483,412 | 104,886 |
Risk Indicators
VVB-confirmed investment/combined test; capture not legally required
reversal events not addressed
0% deduction; justification contradictory across documents
Project-specific, modeled; reassessed at 2021 validation
Grievance mechanism and benefit sharing present; FPIC not conducted per validation report
CCP approved; CORSIA eligibility not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.