Taishan BCCY New Energy Co., Ltd Taishan Xiadoukeng 5MW Biogas Power Generation Project
#207of 268 in Biogas#980of 1084 in China#1119of 1339 in Verra (VCS)#122of 159 in ACM0001
Audit Analysis
A 5 MW landfill gas-to-power project under VCS methodology ACM0001 v19.0, validated by Applus+ Certification, with a 10-year crediting period starting February 2023. The project carries significant unresolved issues: nine material findings, eight corrective actions, and two inter-document contradictions (on leakage treatment and whether gas capture is legally mandated) that undermine confidence in the additionality and baseline claims. No monitoring data, buffer pool allocation, or FNRB methodology has been reported, and the project remains in an early documentation stage.
Red Flags
- Contradiction between the validation report (capture not legally required) and an appendix (capture legally required) directly challenges the additionality claim; the VVB itself flagged 'Lack of Evidence on Legal Requirement for Methane Destruction' as a material finding.
- Nine material findings and eight corrective actions remain in the validation record, including absence of a flare system, unverified MCF value, and data inconsistencies in the f_y parameter and methane destruction deduction.
- Leakage treatment is contradictory: the validation report states leakage is 'deemed negligible' (0% deduction) while an appendix references a 'quantified' approach, leaving the actual treatment ambiguous.
- No monitoring period, verified ERR, or FNRB methodology has been reported; the project has no post-registration performance data.
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-verified but legally-required-capture contradiction unresolved
reversal risk declared N/A without detail
0% deduction with contradictory justification across documents
Project-specific modeled baseline; reassessment not yet due (10-yr interval)
FPIC conducted, grievance mechanism present, safeguards documented
CORSIA and CCP status both unstated; dual-channel risk unassessed
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →