Three Gorges New Energy Jiuquan Co., Ltd Guazhou 100MW Solar Power Project
#634of 1935 in Renewable energy#305of 1084 in China#371of 1339 in Verra (VCS)#492of 1287 in ACM0002
Audit Analysis
A 100 MW solar PV project under VCS methodology ACM0002 with a jurisdictional grid-emission-factor baseline and a VVB-confirmed combined additionality test. The project delivers close to its pro-rata expectation (≈99%), but the verification record contains multiple material findings, eight corrective actions, and several cross-document contradictions that erode confidence in data quality and documentation rigour.
Red Flags
- The 2022 verification report applied a 2 % materiality threshold instead of the 5 % required for projects with ER ≤ 300,000 tCO₂e/yr, meaning some errors may have gone undetected.
- Eleven material findings and eight corrective actions were raised across verification cycles, including inconsistent energy values between the monitoring report and meter records, and a calibration-validity gap in MR v01.
- The crediting period is stated as 2013-2023 (10 yr) in the 2022 verification report but 2012-2032 (20 yr) in a 2015 document, creating ambiguity about the project's actual crediting window.
- Leakage justification shifted from 'quantified' (2020 verification) to 'deemed negligible' (2022 verification) without a clear documented rationale for the change.
- Minimum extraction confidence is rated low, indicating at least one key document was poorly readable during data extraction.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2014 | 105,953 | 103,692 | 2,261 | |
| 2015 | 68,840 | 66,987 | 1,853 | |
| 2016 | 49,940 | 49,335 | 605 | |
| 2017 | 82,087 | 82,079 | 8 | |
| 2018 | 90,816 | 57,696 | 33,120 | |
| 2019 | 40,737 | 40,737 | 0 | |
| 2020 | 85,392 | 17,273 | 68,119 | |
| 2021 | 127,153 | 101,837 | 25,316 | |
| 2022 | 84,396 | 29,528 | 54,868 | |
| Total | 735,314 | 549,164 | 186,150 |
Risk Indicators
VVB-confirmed combined test
Not applicable – solar PV, no biogenic carbon
0 % deduction, deemed negligible for solar
Jurisdictional grid EF, reassessment date not stated
Grievance mechanism present, FPIC not stated
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →