Tradewater International Dominican Republic
#40of 189 in Methane#2of 6 in Dominican Republic#491of 1339 in Verra (VCS)
Audit Analysis
This is a one-time ODS destruction project (VM0016) in the Dominican Republic with inherently low permanence and leakage risk, and VVB-confirmed additionality. However, the verification report identified five material findings including incorrect GWPs, a missing eligible substance (R-115), and erroneous T&D factors, indicating significant calculation and documentation weaknesses in the project design. The PDD's initial ERR claim of 40,000 tCO₂e was reduced to 23,656.86 tCO₂e upon verification, suggesting the initial overstatement was caught, but the underlying calculation errors raise residual accuracy concerns.
Red Flags
- Five material findings in the verification report, including failure to use AR5 GWPs as required by VCS Standard 4.1, omission of eligible R-115 from ER calculations, and incorrect T&D default factors for R-12 and R-114
- PDD claims 40,000 tCO₂e while the validation report and monitoring report both state 23,656.86 tCO₂e — a 41% overstatement in the preliminary document
- Leakage justification is inconsistent between documents: the monitoring report describes it as 'quantified' while the validation report characterises it as 'deemed negligible', despite a 0% deduction in both
- CORSIA eligibility and CCP status are not stated in any available document, leaving dual-channel risk unassessed
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2021 | 23,657 | 3,000 | 20,657 | |
| Total | 23,657 | 3,000 | 20,657 |
Risk Indicators
Combined test, VVB-confirmed
One-time destruction, no reversal risk
0% deduction, justification wording inconsistent
Project-specific, no reassessment date stated
Mentioned and benefit sharing described, FPIC/grievance not
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →