Yamanli III Hydoeletric Power Plant
#89of 295 in Turkey#203of 1339 in Verra (VCS)#305of 1287 in ACM0002
Audit Analysis
The Yamanli III hydroelectric project is a fundamentally sound renewable energy credit with confirmed additionality, no reversal risk, and a conservative baseline that delivered 134% of the pro-rata ex-ante expectation. However, the project carries a heavy burden of documentation inconsistencies (20 corrective actions, 7 cross-document contradictions), a project-specific rather than jurisdictional baseline, and material findings that down-scored social and environmental indicators including ichthyofauna monitoring and population displacement.
Red Flags
- Grid emission factor discrepancy of ~18% between the verification report (0.4476) and the monitoring report (0.547), which directly affects credit quantities
- Ichthyofauna indicator down-scored from 5 to 1 because fish monitoring was not scheduled, indicating an unaddressed environmental impact
- 20 corrective actions remain open, including a requirement to apply a valid version of ACM0002 (v10 no longer valid) and to follow VVB rotation rules
- Baseline method contradicts between documents: project-specific (verification report) vs jurisdictional (validation report), weakening baseline robustness
- Population displacement indicator down-scored due to expropriation and compensation negotiations still in progress
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test
Hydro – no reversal risk
0% – negligible for hydro
Project-specific; method contradicts across docs
FPIC & grievance present; ichthyofauna & displacement down-s
CORSIA & CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →