Yangchun Landfill Gas Power Generation Project
#124of 189 in Methane#901of 1084 in China#1031of 1339 in Verra (VCS)#110of 159 in ACM0001
Audit Analysis
The Yangchun Landfill Gas Power Generation Project is a registered VCS project under the well-established ACM0001 methodology with a reputable VVB (Applus+), but it carries moderate data-reliability concerns stemming from five inter-document contradictions, five material findings at validation, a thin leakage justification, and a low extraction confidence rating. The project delivered roughly 92% of its pro-rata ex-ante expectation for the elapsed monitoring period, which is a reasonable and slightly conservative outcome. Overall, the project is functional but sits in the lower-middle quality band due to documentation gaps and unresolved discrepancies.
Red Flags
- Contradiction between the PDD (capture legally required = true) and the validation report (capture legally required = false) directly undermines the additionality claim; the validation report (2023-04-24) is privileged as the more recent VVB assessment, but the PDD statement raises a residual risk that the project may not be additional.
- Five material findings at validation, including the monitoring plan not meeting ACM0001 requirements, incomplete no-net-harm controls, and a missing baseline parameter (FCH4,BL,R,y), indicate significant documentation gaps at the time of validation.
- Leakage deduction of 0% is justified only as 'deemed negligible' with no quantified analysis, which is thin for a landfill gas collection system where gas escape is a realistic risk.
- No buffer pool percentage is stated in any available document, leaving permanence risk unquantified despite the 'not applicable' reversal statement.
- Minimum extraction confidence is rated low, meaning at least one key document was poorly readable, reducing confidence in the extracted data.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2021 | 10,294 | 0 | 10,294 | |
| 2022 | 1 | 0 | 1 | |
| 2023 | 39,705 | 0 | 39,705 | |
| Total | 50,000 | 0 | 50,000 |
Risk Indicators
VVB-confirmed but PDD/validation conflict on legal requirement
mixed evidence / unresolved risk
0% deduction, 'deemed negligible' only, no quantified analysis
Project-specific, measured/modelled contradiction, no reassessment date
Grievance mechanism and benefit sharing present; FPIC not stated
CORSIA and CCP eligibility both not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →