1.2 MW Biomass Gasification Power Generation Project in Vadodara District of Gujarat, India

CDM-7331 ↗

#168of 352 in Biomass#748of 975 in India#1124of 1459 in CDM (UNFCCC)#452of 806 in AMS-I.D

4.5/ 10
Integrity
5.5
Transparency
3.0
Claim Safety
5.0
Documentation
3.5

Audit Analysis

A 1.2 MW biomass gasification CDM project in Gujarat, India, with a VVB-confirmed investment additionality test and a reasonable grid emission factor, but significant gaps in monitoring data, permanence mechanisms, and baseline robustness. The project-specific baseline and 0% leakage deduction, combined with the complete absence of verified monitoring results, limit confidence in the claimed 62,565 tCO₂e over the 10-year crediting period.

Red Flags

  • No monitoring reports or verified ERR figures found in any available document — the 62,565 tCO₂e claim is entirely unverified
  • Contradiction between the PDD (jurisdictional baseline) and the validation report (project-specific baseline) on baseline method
  • 12 Corrective Action Requests were raised during validation, indicating substantial initial documentation deficiencies (all subsequently closed)
  • Low extraction confidence across the document set, suggesting key data may be missing or unreadable

Credit Vintages

No issuances recorded on the registry.

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

no reversal data

Leakage

0% deduction, 'deemed negligible' — thin justification

Baseline

Project-specific baseline; PDD/VVB contradiction

Safeguards

Safeguards and benefit sharing mentioned; no FPIC or grievance mechanism

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-01AMS I.D

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents