10 MW Biomass based Power Plant by Sanjog Sugars & Eco-Power Private Limited
#67of 352 in Biomass#449of 975 in India#631of 1459 in CDM (UNFCCC)#292of 806 in AMS-I.D
Audit Analysis
A 10 MW seasonal biomass power plant in India under CDM with a VVB-confirmed investment additionality test and a jurisdictional grid baseline. However, the project carries significant documentation quality concerns (eight corrective action requests at validation), a grid emission factor frozen at 2011 levels despite an 11-year crediting window in a rapidly decarbonising grid, a 0% leakage deduction justified only as 'deemed negligible' that contradicts the PDD's quantified approach, and no verified ERR figure available to confirm the 304,951 tCO₂e claimed.
Red Flags
- Grid emission factor of 0.84 tCO₂/MWh was set in 2011 and never updated across the full 2012–2022 crediting period, despite India's grid becoming substantially cleaner; this risks systematic over-crediting.
- Eight corrective action requests (CARs) at validation revealed errors in the investment analysis, grid EF calculation, baseline description, and monitoring plan — all resolved but indicating weak initial project design quality.
- No verified ERR figure is available in the extracted record; the 304,951 tCO₂e claimed in the monitoring report cannot be independently confirmed.
- Leakage justification is contradictory: the PDD quantified leakage while the monitoring report (2023) labels it 'deemed negligible' with a 0% deduction, with no quantified basis provided.
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test
energy project (lower risk)
0% deduction, 'deemed negligible'; PDD contradiction
Jurisdictional but grid EF frozen at 2011 levels
Safeguards mentioned; FPIC and grievance mechanism not stated
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →