Audit Analysis
A 12 MW small-scale mini-hydro project in Andhra Pradesh registered under the UCR voluntary registry, using the well-established AMS-I.D methodology with a jurisdictional baseline and a reasonable 0% leakage deduction. However, the available record consists solely of a Project Design Document; no verification report, monitoring report, or VVB identification was found, leaving additionality, verified emissions reductions, and CORSIA/CCP eligibility entirely unconfirmed.
Red Flags
- No additionality test type or VVB confirmation found in the available PDD; the AMS-I.D methodology requires an investment or barrier test, but no evidence of its completion is present in the extracted record.
- No verified emissions reduction figure is available to cross-check against the 37,843 tCO₂e claimed over the 2014–2021 crediting period, making over- or under-crediting impossible to assess.
- Only a single document (the PDD dated May 2022) was used; no verification report, monitoring report, or VVB identification appears in the record.
Credit Vintages
Issuance data not yet available — check back soon.
Risk Indicators
Test not found in available PDD
Hydro project – inherently low reversal risk
0% deemed negligible – appropriate for hydro
Jurisdictional method stated; reassessment timing not stated
Safeguards mentioned; FPIC and grievance mechanism not stated
CORSIA and CCP status both not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →