13.95 MW grid connected wind electricity generation by SRF Limited
Score Breakdown
Integrity
verified Additionality was tested using an investment test and was confirmed by the VVB in the monitoring report.
missing Leakage justification is not addressed, and reversal events are not addressed in the extracted record.
Transparency
verified A named VVB is identified, and the monitoring period is clearly stated in the monitoring report.
missing Total ERs claimed are not stated, and the record does not provide a usage monitoring method or registry completeness details.
Claim Safety
verified The project is not CORSIA-eligible, which reduces one channel of double-claim risk.
missing The baseline is project-specific rather than a recently reassessed standardized baseline, and leakage treatment is missing.
Documentation
verified Multiple official documents were used, including the PDD, validation report, monitoring report, and issuance record.
missing The monitoring report lists several corrective actions, and extraction confidence is not an issue, but the crediting period contradiction still weakens the record.
Detailed Analysis
Integrity
The monitoring report confirms additionality through an investment test and says the VVB verified it, which supports the project’s core integrity case. However, leakage justification is not addressed, buffer pool coverage is not found, and reversal events are not addressed in the extracted record, so permanence and leakage controls remain weakly evidenced. The project also uses a project baseline, but no baseline reassessment date is stated in available documents.
Transparency
The record identifies the VVB as LGAI Technological Center, S.A. (Applus+ Certification) and gives a clear monitoring period from 2012-03-16 to 2018-02-28. Still, total ERs claimed are not stated, the usage monitoring method is not found, and the extracted record does not show a complete registry trail. These gaps limit how fully an outside reviewer can reconstruct the issuance basis.
Claim Safety
Claim safety is helped by the fact that the project is marked not CORSIA-eligible, which lowers one route to overlapping claims. But the baseline remains project-specific, leakage treatment is missing, and the monitoring report includes corrective actions related to double counting and emission reduction sheet cross-checks. That combination leaves a meaningful over-crediting and claim-quality concern.
Documentation
Documentation is reasonably broad, with evidence drawn from the issuance record, PDD, validation report, and monitoring report, and the extraction confidence is high. Even so, the monitoring report lists multiple corrective actions, including missing host-country authorization, turbine location details, and double-counting declarations, which suggests the file was not fully clean. The crediting period also conflicts between the monitoring report and the PDD, so I privileged the later monitoring report because it is more recent and operationally specific.
Overall
Overall, this is a functioning registered wind project with some solid evidence on additionality and safeguards, but the file is weakened by missing leakage treatment, incomplete permanence evidence, and several corrective actions in the monitoring report. I privileged the monitoring report over the older PDD where the crediting period differs, because it is more recent and closer to issuance, but the contradiction itself still lowers reliability. The integrity score stays below mid-range because the documentation does not fully resolve baseline, leakage, and double-counting concerns.
Audit Analysis
This is a registered VCS wind project with VVB-verified additionality, but the record leaves important gaps on leakage treatment, permanence handling, and baseline reassessment. The project has some safeguard evidence, yet the monitoring report also shows multiple corrective actions and a contradiction on the crediting period that reduces confidence in the documentation trail.
Project Description
Proponent: SRF Limited Protocol categories: Energy industries (renewable/non-renewable sources) Protocols: AMS-I.D. Estimated annual GHG reductions: 34886 tCO2e Region: Asia Registration date: 2020-04-06
Red Flags
- Leakage is not addressed and no leakage deduction is stated in the extracted record.
- The monitoring report lists multiple corrective actions, including double-counting, commissioning date, and grievance register issues.
- A contradiction exists on the crediting period between the monitoring report and the PDD, which weakens reliability.
Credit Vintages
Nessuna emissione registrata sul registro.
Cosa migliorerebbe questo punteggio
- Provide a clear leakage assessment and, if applicable, a quantified deduction with justification.
- Publish a reconciled issuance package that resolves the crediting-period contradiction and closes the corrective actions on double counting, commissioning date, and grievance records.
Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.
Risk Indicators
VVB-confirmed investment test
No reversal evidence, but buffer not stated
Leakage not addressed
Project baseline, reassessment not stated
FPIC and grievance noted, but inconsistently documented
Not CORSIA-eligible, CCP status not stated
Where to buy
+ Know where to buy this?
Listing multiple projects? Send us a CSV at [email protected].
⚑ Dispute this rating
Registry Documents
Sei il proprietario di questo progetto?
Correzione metadati (gratuita)
Nome, paese, marketplace o link errati? Segnalacelo.
Non modifica lo score.
[email protected] →Rivalutazione con nuovi documenti
Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.
Invia Documenti →