2.45 MW Wind Power Project in Rajasthan, India by Yamuna Power and Infrastructure Ltd.
#165of 1935 in Renewable energy#77of 975 in India#66of 1339 in Verra (VCS)#56of 806 in AMS-I.D
Audit Analysis
A 2.45 MW wind power project in Rajasthan with a VVB-verified investment additionality test and a straightforward grid-displacement claim. The project's main weaknesses are a baseline method contradiction between the 2022 verification and monitoring reports, a 0% leakage deduction with no explicit justification in the latest report, and the absence of FPIC. Overall a moderate-quality renewable energy credit with minor data inconsistencies.
Red Flags
- Baseline method is stated as 'project' in the 2022 verification report but 'jurisdictional' in the 2022 monitoring report — an unresolved contradiction that affects baseline robustness
- Leakage deduction is 0% with justification recorded as 'not addressed' in the 2022 verification report, downgraded from 'deemed negligible' in the 2011 report
- FPIC was not conducted, and the 2009 validation report records no grievance mechanism or safeguards, creating a gap in social safeguards documentation
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2006 | 3,319 | 3,319 | 0 | |
| 2007 | 3,392 | 3,392 | 0 | |
| 2008 | 3,567 | 3,567 | 0 | |
| 2009 | 2,818 | 2,818 | 0 | |
| 2010 | 2,756 | 2,756 | 0 | |
| 2011 | 2,892 | 2,892 | 0 | |
| 2012 | 2,693 | 2,693 | 0 | |
| 2013 | 2,697 | 2,697 | 0 | |
| 2014 | 2,758 | 2,758 | 0 | |
| 2015 | 2,095 | 2,095 | 0 | |
| 2016 | 364 | 304 | 60 | |
| Total | 29,351 | 29,291 | 60 |
Risk Indicators
VVB-verified investment test
Avoidance project, no reversal risk
0% deduction, justification not addressed in 2022 report
Project-specific, method contradicted across 2022 docs
Grievance mechanism present, FPIC not conducted
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →