2.45 MW Wind Power Project in Rajasthan, India by Yamuna Power and Infrastructure Ltd.

VCS-308 ↗

6.2 / 10
Integrity
6.1
Transparency
6.4
Claim Safety
5.8
Documentation
6.8

Score Breakdown

Integrity

verified Additionality was tested using an investment test and was confirmed by the VVB in the monitoring record.

missing Leakage justification is not addressed in the later monitoring report, and no leakage deduction percentage is stated.

Transparency

verified The project has a named VVB, a defined monitoring period, and claimed and verified emissions reductions are both reported.

missing The record does not state a usage monitoring method, and the baseline was not shown to have been recently reassessed.

Claim Safety

verified The project is a renewable wind project with a project baseline and no reversal events reported in the extracted record.

missing Leakage treatment is weak or inconsistent, and the project is not CORSIA-eligible, which limits claim safety.

Documentation

verified The extraction draws on multiple official documents, with 21 documents used and high extraction confidence.

verified No material findings or corrective actions were reported in the available verification record.

Detailed Analysis

Integrity

The monitoring record confirms additionality through an investment test and says the VVB verified it, which supports the core project case. No material findings or corrective actions were reported, but the record does not state a buffer pool, reversal events, or a leakage deduction percentage, and leakage is explicitly marked as not addressed in the later monitoring report. The baseline is project-based, but the last reassessment date is not stated in the extracted documents.

Transparency

The project has a named verifier, Earthood Services Private Limited, and the monitoring period and crediting period are both stated. Claimed and verified emissions reductions are both 17,450 in the extracted monitoring record, which helps traceability, but the usage monitoring method is not stated and the grid emission factor year is missing. The documentation is reasonably complete, though not fully transparent on operational monitoring details.

Claim Safety

As a wind power project under a project baseline, the core claim is straightforward, but the absence of a stated leakage deduction and the later note that leakage was not addressed weaken over-crediting protection. The project is not CORSIA-eligible, which reduces dual-market claim risk, but CCP status is not stated. No reversal events are reported, which is appropriate for an avoidance-style renewable project.

Documentation

The evidence base is fairly strong, with 21 documents used and high extraction confidence. The record also shows no material findings and no corrective actions required in the available verification material. Documentation quality is weakened by missing specifics on baseline reassessment, leakage treatment, and usage monitoring, but overall it is better than average.

Overall

The project scores in the middle range because the additionality case is supported and the documentation set is substantial, but several key risk controls are incomplete. I privileged the more recent monitoring report for safeguards, FPIC, and leakage treatment because it is later and more operationally specific, while noting that it conflicts with an earlier validation report that appears to have been more restrictive on those points. I also treated the differing verified emissions reduction figures as a reliability issue and reduced confidence accordingly.

Audit Analysis

This is a registered VCS wind project with VVB-confirmed investment-test additionality and no material findings reported in the available verification record. However, leakage is not addressed in the later monitoring record, baseline reassessment is not stated, and there are contradictions across documents on safeguards and the verified emissions reduction figure, which reduce confidence in the claim quality.

Project Description

Proponent: Yamuna Power & Infrastructure Limited Protocol categories: Energy industries (renewable/non-renewable sources) Protocols: AMS-I.D. Estimated annual GHG reductions: 3921 tCO2e Region: Asia Registration date: 2020-04-06

Red Flags

  • The later monitoring report says leakage was not addressed, while an earlier monitoring report reportedly quantified it, creating a documentation inconsistency.
  • The verified emissions reduction figure differs across validation-related documents, and the project is not CORSIA-eligible.

Credit Vintages

Issued Retired Available
2006
3,319 3,319 0
2007
3,392 3,392 0
2008
3,567 3,567 0
2009
2,818 2,818 0
2010
2,756 2,756 0
2011
2,892 2,892 0
2012
2,693 2,693 0
2013
2,697 2,697 0
2014
2,758 2,758 0
2015
2,095 2,095 0
2016
364 304 60
Total 29,351 29,291 60

Cosa migliorerebbe questo punteggio

  • Provide a clear, dated leakage assessment and any deduction applied, with reconciliation to the earlier monitoring record.
  • Publish the baseline reassessment history, usage monitoring method, and a document trail explaining the emissions reduction figure discrepancy.

Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

No reversal events reported

Leakage

Leakage not addressed consistently

Baseline

Project baseline, reassessment not stated

Safeguards

FPIC and grievance present, but contradictory

Double-claim

Not CORSIA-eligible; CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis Provenance Scored 2026-04-14 General Methodology v2.0 Documentazione completa

Sei il proprietario di questo progetto?

Correzione metadati (gratuita)

Nome, paese, marketplace o link errati? Segnalacelo.

Non modifica lo score.

[email protected]

Rivalutazione con nuovi documenti

Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.

Invia Documenti