2 MW Kalm Small Hydro Electric Project in Himachal Pradesh, India
#811of 1935 in Renewable energy#408of 975 in India#570of 1459 in CDM (UNFCCC)#276of 806 in AMS-I.D
Audit Analysis
A 2 MW small hydro project under CDM with a VVB-verified investment additionality test and a standardised AMS-ID methodology, but the available record contains no monitoring or verified-credit data, a baseline-method contradiction between the PDD and validation report, and low extraction confidence across the document set. The project is an avoidance-type credit (displacing grid electricity) with negligible reversal risk, and the 20 material findings raised during validation were all administrative or financial corrections that were subsequently addressed.
Red Flags
- Baseline method contradiction: the PDD (Nov 2011) describes a jurisdictional baseline while the validation report (Dec 2011) records a project-specific baseline; the more recent and authoritative validation report is privileged, but the discrepancy weakens baseline confidence.
- No monitoring-period data or verified ERR figures are present in the extracted record, making it impossible to confirm actual credit delivery against the 83,480 tCO₂e lifetime claim.
- Low extraction confidence across the document set indicates at least one key document was poorly readable, reducing reliability of the structured facts.
- Leakage treatment contradiction: an appendix (Jan 2010) references a quantified leakage assessment while the validation report (Dec 2011) records leakage as deemed negligible with a 0% deduction.
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test
Avoidance project, no reversal risk
0% deemed negligible; minor doc contradiction
Project-specific per VR; PDD said jurisdictional
Mentioned; FPIC and grievance not detailed
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →