Skip to main content
CDMBiomass EnergyIndiaACM0006

20 MW Bagasse Based Co-generation Power Project at Bannari Amman Sugars Limited, Nanjangud, Karnataka

CDM-1574 ↗

#195of 352 in Biomass#805of 975 in India#1216of 1459 in CDM (UNFCCC)#29of 81 in ACM0006

4.3/ 10
Integrity
6.0
Transparency
2.0
Claim Safety
5.5
Documentation
2.5

Audit Analysis

A 20 MW bagasse co-generation CDM project in Karnataka with a solid VVB-confirmed barrier additionality test and reasonable leakage treatment, but severely limited documentation — only a 2008 validation report is available with no monitoring or verification data. CORSIA eligibility introduces dual-channel risk, and the project-specific baseline (flagged for transparency issues during validation) weakens the overall credit quality.

Red Flags

  • No monitoring or verification reports are available; only the 2008 validation report and an appendix exist, leaving the 721,580 tCO2e lifetime claim entirely unverified against actual performance
  • CORSIA eligibility is confirmed while CCP status is not stated, creating a dual-channel allocation risk for the same credits
  • CAR13 during validation noted that the baseline discussion in the PDD was not transparent and required a revised PDD to clarify baseline scenario 16, indicating a project-specific baseline that was not straightforward

Credit Vintages

No issuances recorded on the registry.

Risk Indicators

Additionality

Barrier test confirmed by SGS UK

Permanence

Waste feedstock, no reversal data

Leakage

0% deemed negligible, consistent with bagasse

Baseline

Project-specific, CAR13 transparency issue

Safeguards

FPIC, grievance mechanism, safeguards documented

Double-claim

CORSIA-eligible, CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-24ACM0006

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents