ACM0006 — Electricity and heat generation from biomass

About this methodology

Projects use biomass to produce heat and electricity, including through upgrades or changes of fuel. The method measures emission reductions against the energy supply that would otherwise be used.

Version
16.0 · source ·
Status
Active at CDM / UNFCCC · source ·
Climate outcome
Emission reductions
Activity
Industrial energy
Official page
cdm.unfccc.int ·
Also used by projects of
3 more

How methodology v3 reads projects of this type

What CarbonMeld reads

  • shown

    Grid emission factor: the methodology sets rules for it in some cases (TOOL07 for electricity displaced in the grid, p. 7). CarbonMeld reads it in the project's documents. CM-F-ACM0006-GRID-EF

    Link
  • A confirmed investment analysis A-INVEST

    The documents show a project-level additionality test, the validation confirmed it, and it is an investment analysis (a numeric test of the project's finances with and without carbon revenue).

Deductions that can apply

  • No additionality test in the documents (renewable energy) A-TEST-NOT-STATED

    Renewable energy, power generation and supply: the documents read state no additionality test. A test that the documents do not name is a different case. It takes no points. CarbonMeld applies this rule only where a check of the documents has confirmed its condition; without that check, the rule takes no points.

Set by the methodology or the programme, not assessed by our current method

  • not assessed

    Leakage: the methodology sets rules for it (ACM0006 v16 §5.7, p. 37). Our current method does not assess it. CM-F-ACM0006-LEAKAGE

    Link
  • not assessed

    Social safeguards and consent of communities (FPIC): any such rules come from the programme, not the methodology. Our current method does not assess it. CM-F-ACM0006-SAFEGUARDS-FPIC

    Link

Not applicable to this type — never a gap in our current method

The criterion does not apply to this methodology. Our current method never counts it as a gap.

The general rules apply as well. Read the general rules.

The rules of methodology v2.2, as they were: the archived v2.2 page.

History and transitions

All 24 versions · current v16.0
  • v16.0adopted 11 Mar 2022currentsource

    Indicate the emission sources that are relevant in the calculation of project emissions associated with biomass and biomass residues, in line with “TOOL16: Project and leakage emissions from biomass” (version 05.0); Make editorial …

  • v15.0adopted 14 Dec 2020source

    Address inconsistencies and ambiguities in the language used in some parts of the methodology; Simplify the approach for the estimation of emission reductions.

  • v14.0adopted 29 Nov 2018source

    Include non-binding best practice examples.

  • v13.1adopted 31 May 2017source

    Editorial revision to correct paragraph numbering.

  • v13.0adopted 4 May 2017source

    Add reference to the methodological tool “Project and leakage emissions from biomass” (TOOL16); Streamline the provisions associated with cultivation of biomass from a dedicated plantation.

  • v12.1.1adopted 13 Sept 2012source

    Amendment to: Broaden the applicability of the methodology to utilization of biomass from dedicated plantations; Change the title from “Consolidated methodology for electricity and heat generation from biomass residues” to “Consolidated …

  • v12.1.0adopted 2 Mar 2012source

    Editorial amendment to modify equations in pages 36 and 39 where the amount of electricity generated in the baseline is higher than the amount of energy generated in the project activity.

  • v12.0adopted 2 Mar 2012source

    Revision in order to incorporate reference to the tools: “Assessment of the validity of the original/current baseline and update of the baseline at the renewal of a crediting period”; “Tool for project and leakage emissions from road …

  • v11.2adopted 29 Sept 2011source

    Amendment to: Broaden the applicability of the methodology to situations where mechanical energy is produced from process heat generated from biomass; Broaden the applicability of the methodology by increasing the maximal share of the …

  • v11.1adopted 26 Nov 2010source

    The methodology was revised in order to include project activities that use biogas produced from anaerobic digestion of wastewater as fuel. The revision also corrects editorial mistakes in equations and definitions of parameters.

  • v11.0adopted 17 Sept 2010source

    The revised methodology, now titled “Consolidated methodology for electricity and heat generation from biomass residues”, is made in response to the EB 37 request to undertake a review of ACM0006 with a view to: (i) Provide more clarity on …

  • v10.1adopted 30 Jul 2010source

    Editorial revision to: Revise the monitoring procedure of the biomass moisture content so that the parameter can be monitored for each batch of biomass, rather than continuously.

  • v10.0adopted 12 Feb 2010source

    The applicability of the methodology was restricted to power and heat projects due to the approval of a new consolidated methodology ACM0018 for power-only projects. Power-only projects were excluded from this methodology.

  • v09.0adopted 17 Jul 2009source

    Equation 15 was divided into two different equations in order to be correctly applied in case of scenario 13.

  • v08.0adopted 25 Mar 2009source

    Scenario 22 was included in the methodology in response to the request for revision AM_REV_0118. Furthermore, scenario 21 was wrongly mentioned in the field “Any comment” in the table for parameter BFk,boiler,historic,3yr which was …

  • v07.0adopted 13 Feb 2009source

    The methodology was revised to include the following requests for revision and clarifications: AM_REV_0074 - inclusion of Scenario 21; AM_CLA_0065 - the statement “the efficiency of heat generation in the project plant is smaller or the …

  • v06.2adopted 2 Aug 2008source

    The title of the “Tool to determine methane emissions avoided from dumping waste at a solid waste disposal site” changes to “Tool to determine methane emissions avoided from disposal of waste at a solid waste disposal site”.

  • v06.1adopted 16 May 2008source

    “Tool to calculate baseline, project and/or leakage emissions from electricity consumption” replaces the withdrawn “Tool to calculate project emissions from electricity consumption”.

  • v06.0adopted 27 Aug 2007source

    The methodology was revised: To have its applicability broadened to project activities that install a new cogeneration facility using biomass; To modify the equation for baseline methane emissions from avoided dumping of biomass residue to …

  • v05.0adopted 18 May 2007source

    The methodology was revised in response to the request AM_REV_0044 to expand the applicability of the approved methodology by including new scenario for project activities that improve the efficiency of biomass use in generating …

  • v04.0adopted 2 Nov 2006source

  • v03.0adopted 19 May 2006source

    Inclusion of definitions section; The methodology was revised in order to clarify the process for estimating the net quantity of increased electricity from implementation of project activity under Scenario 14.

  • v02.0adopted 3 Mar 2006source

    Inclusion of the name of the project developer; Inclusion of Scenario 16.

  • v01.0adopted 30 Sept 2005source

    Initial adoption.

Top projects using ACM0006

This page ranks projects using ACM0006 by their CarbonMeld document-based ratings. The rank compares project ratings; it is not a rating of the methodology itself.

7 rated projects of the 504 tracked in this methodology · average rating 3.5/10 · ranked by CarbonMeld's document-based rating: additionality, quantification, permanence (where carbon is stored) and claim safety.

127 analysed project pages, A–Z →

Which registries list projects under ACM0006?

In CarbonMeld's data, ACM0006 projects are on 7 registries: CDM (417), Verra (41) and Universal Carbon Registry (38), and 4 more. Being listed on a registry is not the same as being registered: the «Registered» column counts the projects each registry shows as registered, and credits are issued only after each verification.

RegistryProjectsRegisteredProjects list
CDM (UNFCCC)417143See the list
Verra (VCS)4110See the list
Universal Carbon Registry (UCR)3821See the list
Gold Standard (GS)51See the list
CerCarbono (CC)10See the list
Global Carbon Council (GCC)10See the list
International Carbon Registry (ICR)10See the list

Counts of project records in CarbonMeld's data, with or without a CarbonMeld analysis, so they can be larger than the ranking below. «Registered» counts the records whose current registry status is «registered», as last read (24 November 2026); projects in a later status, such as awaiting verification approval, late to verify or completed, are not in that column.

#1 Biomass Cogeneration Plant By SCOUL VCS Uganda Biomass Registry: Registered 3.9/10 #2 Henan Xinxiang 24MW Biomass Based Cogeneration Project VCS China Biomass Registry: Registered 3.6/10 #3 Liucheng Biomass Power Generation Project In Guangxi Zhuang Autonomous Region, China VCS China Biomass Registry: Registered 3.6/10
  1. 4 3.6
  2. 5
    5MW Biomass Based Cogeneration Project At Sainsons VCS India Biomass Registry: Registered
    3.6
  3. 6
    15 MW Biomass Residue Based Power Project At Ghazipur, India VCS India Biomass Registry: Registered
    3.3
  4. 7
    VIÑALES BIOMASS POWER PLANT VCS Chile Biomass Registry: Registered
    3.2