3.3 MW Wind Power Project in India

CDM-6445 ↗

#588of 1935 in Renewable energy#287of 975 in India#393of 1459 in CDM (UNFCCC)

5.6/ 10
Integrity
6.5
Transparency
4.0
Claim Safety
6.5
Documentation
4.5

Audit Analysis

A 3.3 MW onshore wind project in India registered under CDM with a jurisdictional grid baseline and VVB-confirmed investment additionality. The project's core design is sound for a wind avoidance project, but the extracted record contains no monitoring or verification data, and the validation report flagged eight material findings that required corrective action before registration. Overall, the project is structurally credible but the evidence base available for scoring is thin.

Red Flags

  • Eight material findings (CARs) were raised during validation, including missing justification for the simple operating margin, PDD sections not following CDM-SSC-PDD guidelines, and monitoring practices in the PDD not reflecting actual site practices for electricity apportionment.
  • No monitoring report or verified ERR figure is present in the extracted record, making it impossible to confirm actual credit delivery against the 61,170 tCO2e lifetime claim.
  • Grid emission factor is fixed at the 2009 value (0.9225 tCO2/MWh); no evidence of periodic grid EF updates or baseline reassessment is found in the available documents.

Credit Vintages

No issuances recorded on the registry.

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Wind avoidance – no reversal risk

Leakage

0 % deemed negligible – appropriate for wind

Baseline

Jurisdictional grid EF (0.9225, 2009)

Safeguards

Safeguards mentioned; FPIC & grievance mechanism not stated

Double-claim

CORSIA & CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-24General Methodology v2.1

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents