49.5 MW Wind Power Project by FFCEL in Pakistan

VCS-1346 ↗

#245of 1935 in Renewable energy#3of 9 in Pakistan#109of 1339 in Verra (VCS)#178of 1287 in ACM0002

6.2/ 10
Integrity
7.0
Transparency
6.0
Claim Safety
5.0
Documentation
6.5

Audit Analysis

A 49.5 MW wind project in Pakistan with a solid additionality assessment (combined test, VVB-verified) and an appropriate jurisdictional grid-emission-factor baseline. The most recent verification cycle (2023) shows full consistency between claimed and verified ERs, but an earlier 2022 report reveals a large gap between claimed (453,091) and verified (65,308) ERs that raises over-crediting concerns. Safeguards documentation improved over time, and the project is explicitly not CORSIA-eligible, reducing double-claiming risk.

Red Flags

  • 2022 verification report shows 453,091 ERs claimed versus only 65,308 verified — a 7:1 gap that may indicate over-claiming or a mismatch between cumulative and per-period bases; the 2023 report (77,293 = 77,293) is consistent but does not resolve the earlier discrepancy.
  • FPIC status is contradictory across documents: the 2015 verification report states FPIC was not conducted, while the 2023 monitoring report states it was. The more recent 2023 record is privileged, but the inconsistency weakens confidence in the safeguards narrative.
  • Baseline method is described as 'project' in the 2014 validation report but 'jurisdictional' in the 2023 monitoring report. The more recent and methodologically appropriate 'jurisdictional' label is privileged, but the discrepancy suggests the baseline characterisation was not consistently documented.

Credit Vintages

IssuedRetiredAvailable
2013
56,79856,7980
2014
95,39195,093298
2015
151,529151,5290
2016
165,532165,5320
2017
77,11977,1190
2018
75,62829,40346,225
2019
70,55070,5500
2020
52,03852,0380
Total744,585698,06246,523

Risk Indicators

Additionality

Combined test, VVB-confirmed

Permanence

Wind avoidance, no reversal risk

Leakage

0% deemed negligible, appropriate for wind

Baseline

Jurisdictional grid EF, but method label inconsistent across docs

Safeguards

Grievance present, FPIC contradictory across reports

Double-claim

Not CORSIA-eligible, CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-09-01ACM0002

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents