5X0.8 MW Wind Power Project by Texmo Industries

CDM-8150 ↗

#1073of 1935 in Renewable energy#554of 975 in India#797of 1459 in CDM (UNFCCC)#347of 806 in AMS-I.D

5.0/ 10
Integrity
5.0
Transparency
4.5
Claim Safety
5.0
Documentation
6.0

Audit Analysis

A 4 MW CDM wind project in India with a verified investment-test additionality and jurisdictional baseline, but undermined by seven material findings in the monitoring report—including two turbines wheeling power to the owner's factory rather than the grid as registered—and an unresolved contradiction in the reported emission reduction figures. The project's operational deviation from its PDD and the absence of a buffer pool or verified ERR figure limit confidence in the integrity and safety of the claims.

Red Flags

  • Two wind turbines (HTSC 1689 and 1707) are wheeling generated power to the project participant's manufacturing plant instead of exporting to the grid as stated in the registered PDD, constituting an operational deviation from the approved project design.
  • The monitoring report (2022-07-06) contains two different total ERR values (6,481 and 44,652) within the same document, creating an unresolved contradiction that undermines confidence in the reported emission reductions.
  • Seven material findings were raised in the monitoring report, including unsupported technical lifetime of the turbines, missing host-country approval for validation, and an unrealistic crediting-period start date, yet no corrective actions are recorded as required.

Credit Vintages

IssuedRetiredAvailable
2014
7,03507,035
Total7,03507,035

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

turbine lifetime unverified

Leakage

0% deemed negligible, appropriate for wind

Baseline

Jurisdictional grid EF, CDM-standard

Safeguards

Safeguards and benefit sharing mentioned; FPIC and grievance

Double-claim

CCP and CORSIA status not stated in available documents

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-25AMS-I.D. Grid connected renewable electricity generation

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents