6 MW biomass based grid connected power generation by M/s Armstrong Energy Pvt. Ltd at Nashik

CDM-4617 ↗

#12of 352 in Biomass#143of 975 in India#176of 1459 in CDM (UNFCCC)#106of 806 in AMS-I.D

6.1/ 10
Integrity
7.2
Transparency
5.5
Claim Safety
6.0
Documentation
5.0

Audit Analysis

A 6 MW biomass-and-coal cogeneration project in Nashik, India, validated under CDM AMS-I.D with a well-supported investment-test additionality and a jurisdictional Combined Margin baseline. The project is structurally sound but carries a notable greenwashing concern from its 20% coal fuel share, and the available record lacks verified emission figures and several monitoring details, compounded by low extraction confidence across the source documents.

Red Flags

  • The project is marketed as 'biomass based' but the validation report confirms a fuel mix of 80% bagasse and 20% coal, meaning roughly one-fifth of the energy input is fossil fuel.
  • Total verified emissions reductions are not found in the extracted record, making it impossible to cross-check the 242,270 tCO2 lifetime claim against actual monitored performance.
  • Minimum extraction confidence is rated low, indicating at least one key document was poorly readable and the structured data may be incomplete.

Credit Vintages

No issuances recorded on the registry.

Risk Indicators

Additionality

VVB-confirmed investment test

Permanence

Avoidance project, no reversal risk

Leakage

Negligible, 25% biomass surplus

Baseline

Jurisdictional Combined Margin

Safeguards

Mentioned but FPIC/grievance not detailed

Double-claim

CORSIA and CCP status not stated

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis ProvenanceScored2026-08-25AMS-I.D

Are you the project owner?

Metadata correction (free)

Name, country, marketplace or links incorrect? Let us know.

Does not modify the score.

[email protected]

Pipeline re-run with new documents

Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.

Submit Documents