6 MW biomass based grid connected power generation by M/s Armstrong Energy Pvt. Ltd at Nashik
#12of 352 in Biomass#143of 975 in India#176of 1459 in CDM (UNFCCC)#106of 806 in AMS-I.D
Audit Analysis
A 6 MW biomass-and-coal cogeneration project in Nashik, India, validated under CDM AMS-I.D with a well-supported investment-test additionality and a jurisdictional Combined Margin baseline. The project is structurally sound but carries a notable greenwashing concern from its 20% coal fuel share, and the available record lacks verified emission figures and several monitoring details, compounded by low extraction confidence across the source documents.
Red Flags
- The project is marketed as 'biomass based' but the validation report confirms a fuel mix of 80% bagasse and 20% coal, meaning roughly one-fifth of the energy input is fossil fuel.
- Total verified emissions reductions are not found in the extracted record, making it impossible to cross-check the 242,270 tCO2 lifetime claim against actual monitored performance.
- Minimum extraction confidence is rated low, indicating at least one key document was poorly readable and the structured data may be incomplete.
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
VVB-confirmed investment test
Avoidance project, no reversal risk
Negligible, 25% biomass surplus
Jurisdictional Combined Margin
Mentioned but FPIC/grievance not detailed
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →