6 MW Harangi Phase-II Hydro Power Project in Karnataka, India
#41of 1935 in Renewable energy#27of 975 in India#27of 1459 in CDM (UNFCCC)#15of 806 in AMS-I.D
Audit Analysis
A straightforward 6 MW run-of-river hydro project in Karnataka, India, validated under CDM with a jurisdictional baseline and VVB-confirmed investment-test additionality. The project over-delivered relative to its pro-rata expectation in the first monitoring period, and no reversal or leakage concerns are apparent for this avoidance-type project. Four corrective action requests during validation (all subsequently resolved) and several unreported monitoring details temper the overall assessment.
Red Flags
- Four corrective action requests (CARs) were raised during validation, including a missing host-country approval letter, an incorrect grid emission factor in the initial PDD, and a flawed investment-barrier/IRR calculation — all resolved but indicative of initial documentation quality issues.
- The crediting-period start date differs by three months between the validation report (2010-06-01) and the monitoring report (2010-08-31), creating ambiguity about the exact project start.
- Several key monitoring parameters (functional no-regret baseline method, usage monitoring method, CORSIA eligibility) are not stated in the extracted record.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2013 | 8,089 | 0 | 8,089 | |
| Total | 8,089 | 0 | 8,089 |
Risk Indicators
VVB-confirmed investment test
Avoidance project, no reversal risk
Deemed negligible, justified
Jurisdictional grid EF (0.85, 2007)
Mentioned but FPIC and grievance mechanism not detailed
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →