GS Solar Thermal - Electricity India Documentazione completa General Methodology v2.0

72 MWac Ramnad Solar Power Project

GS-1427 ↗

4.5 / 10
Integrity
4.8
Transparency
4.3
Claim Safety
4.1
Documentation
5.0

Score Breakdown

Integrity

verified Additionality was confirmed by Earthood Services Private Limited, and the validation report indicates a combined additionality test.

missing The monitoring report records several CARs and CLs, including inconsistent generation and baseline emission figures, and leakage is not addressed there.

Transparency

verified The project has a named VVB and a defined monitoring period from 2021-01-01 to 2022-12-31.

missing Verified and claimed ERR totals are not stated in the extracted record, and the monitoring report shows missing generation data for several months.

Claim Safety

verified The project uses ACM0002 under Gold Standard, which is a recognized methodology for grid-connected renewable power.

missing Leakage treatment is weak because the monitoring report does not address it, even though the PDD describes it as negligible; CORSIA eligibility is true, which keeps dual-use risk relevant.

Documentation

verified The record includes multiple official documents, including the PDD, monitoring report, and validation report, with high extraction confidence.

missing The monitoring report lists several corrective actions and inconsistencies, and the crediting period is inconsistent across documents.

Detailed Analysis

Integrity

Additionality is reasonably supported because the validation report confirms a combined test and the VVB is identified as Earthood Services Private Limited. However, the monitoring report raised multiple CARs and CLs, including missing generation data and inconsistent net generation and baseline emission values, which weakens confidence in the emissions accounting. Leakage is also weakly supported because the monitoring report says it is not addressed, even though the PDD describes it as negligible.

Transparency

The project has a named verifier and a clearly stated monitoring period, which helps traceability. That said, the extracted record does not provide verified or claimed ERR totals, and the monitoring report flags missing generation data for several months. The absence of quantified FNRB, usage-rate, and emission totals limits public-facing transparency.

Claim Safety

Claim safety is moderate at best because the project uses a standard grid-connected solar methodology, but the evidence base for over-crediting control is incomplete. The PDD says leakage is negligible, while the monitoring report does not address leakage, so the record does not show a robust quantified deduction. CORSIA eligibility is true, which means the project sits in a higher-scrutiny category for claim use.

Documentation

Documentation breadth is decent because the record includes the PDD, monitoring report, and validation report, and extraction confidence is high. Still, the monitoring report contains several corrective actions and inconsistencies, including crediting-period and meter-related issues. The crediting period also conflicts between the monitoring report and the PDD, so the documentation is not fully clean.

Overall

I privileged the validation report for additionality because it is the higher-assurance document for that question, while I privileged the monitoring report for leakage and documentation issues because it is the more recent operational evidence. The contradiction on leakage is important: the PDD says it is negligible, but the monitoring report says it is not addressed, so I scored leakage conservatively. The crediting-period contradiction was resolved in favor of the monitoring report as the later document, but it still lowers reliability because the two documents disagree materially.

Audit Analysis

This is a real, VVB-verified solar project with some positive evidence on additionality and safeguards, but the monitoring record shows multiple corrective actions and several unresolved data gaps. The biggest concerns are weak leakage treatment, inconsistent crediting-period information across documents, and missing verified emissions/usage figures in the extracted record.

Project Description

Developer: Infinite Environmental Solutions Limited Type: Solar Thermal - Electricity Size: Large Scale Methodology: ACM0002 Grid-connected electricity generation from renewable sources Crediting period: 2018-10-26 → 2028-10-26 Estimated annual credits: 114663 tCO2e SDGs: Goal 13: Climate Action, Goal 7: Affordable and Clean Energy, Goal 8: Decent Work and Economic Growth

Red Flags

  • The monitoring report raised multiple CARs and CLs, including missing generation data and inconsistent net generation and baseline emissions.
  • Leakage is not addressed in the monitoring report, while the PDD says it is negligible; the record does not show a quantified deduction.
  • The crediting period differs between the monitoring report and the PDD, creating a documentation reliability issue.

Credit Vintages

Issued Retired Available
2021
113,391 0 113,391
2022
107,898 0 107,898
2023
100,303 0 100,303
Total 321,592 0 321,592

Cosa migliorerebbe questo punteggio

  • Provide a reconciled emissions statement with verified ERR totals, meter calibration evidence, and complete generation data for all monitoring months.
  • Document leakage treatment, safeguard evidence, and the corrected crediting period in a single consistent set of project records.

Questi suggerimenti indicano quali prove pubbliche aggiuntive potrebbero migliorare il livello di confidenza di questa valutazione. Non garantiscono un punteggio futuro più alto.

Risk Indicators

Additionality

VVB-confirmed combined test

Permanence

Avoidance project with no reversal evidence

Leakage

Leakage not quantified in monitoring record

Baseline

Project baseline stated, reassessment timing missing

Safeguards

FPIC and grievance mechanism present, but safeguards evidenc

Double-claim

CORSIA-eligible status increases dual-use scrutiny

Where to buy

+ Know where to buy this?

Listing multiple projects? Send us a CSV at [email protected].

⚑ Dispute this rating
Analysis Provenance Scored 2026-04-13 General Methodology v2.0 Documentazione completa

Sei il proprietario di questo progetto?

Correzione metadati (gratuita)

Nome, paese, marketplace o link errati? Segnalacelo.

Non modifica lo score.

[email protected]

Rivalutazione con nuovi documenti

Hai documentazione aggiornata non ancora inclusa? Puoi richiedere un nuovo run della pipeline con i nuovi input.

Invia Documenti