75MW wind power project in Maharashtra by Essel Mining Industries Limited
#742of 1935 in Renewable energy#368of 975 in India#509of 1459 in CDM (UNFCCC)#578of 1287 in ACM0002
Audit Analysis
A 75 MW CDM wind project in Maharashtra with VVB-confirmed additionality and low inherent permanence risk, but undermined by seven material findings in the PDD, unresolved contradictions between the validation and monitoring reports on baseline method and leakage treatment, and the absence of a verified ERR figure. The project's data quality issues and document inconsistencies materially reduce confidence in the claimed emission reductions.
Red Flags
- Seven material findings in the validation report, including incorrect turbine specifications, wrong margin calculation, and generation data that did not match MSEDCL records — all corrected but indicating a weak initial PDD
- Contradiction between the validation report (2007) and monitoring report (2020) on baseline method: 'jurisdictional' vs 'project-specific'
- Contradiction on leakage treatment: validation report states 'deemed negligible' while the monitoring report states 'quantified', yet the deduction is 0% in both cases
- No verified ERR figure found in any available document; only claimed totals are reported
- Grid emission factor of 0.94 tCO2/MWh is drawn from 2005 data, over a decade before the crediting period began
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2011 | 297,066 | 0 | 297,066 | |
| 2013 | 207,941 | 0 | 207,941 | |
| 2014 | 104,685 | 0 | 104,685 | |
| 2017 | 190,298 | 0 | 190,298 | |
| 2021 | 181,824 | 0 | 181,824 | |
| Total | 981,814 | 0 | 981,814 |
Risk Indicators
VVB-confirmed investment test
Wind project, minimal reversal risk
0% deduction, contradictory justifications
Project-specific, grid EF from 2005, no reassessment recorde
Mentioned but FPIC and grievance mechanism not documented
CDM credits; CORSIA/CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →