75MW Yunnan Nuozu Hydropower Project
#913of 1935 in Renewable energy#477of 1084 in China#642of 1459 in CDM (UNFCCC)#714of 1287 in ACM0002
Audit Analysis
The 75MW Yunnan Nuozu Hydropower Project is a fundamentally sound CDM hydro design with a jurisdictional grid baseline and VVB-verified combined additionality test, but its integrity is undermined by five corrective actions and twelve material findings at validation, including inaccurate IRR sensitivity calculations and a non-conservative electricity estimate. Key verification data (verified ERR, FNRB, monitoring method) are absent from the extracted record, limiting transparency. The project delivered roughly 139% of its pro-rata expectation for the 2013–2015 monitoring period, suggesting no over-crediting, but the documentation quality issues and missing safeguards records prevent a higher rating.
Red Flags
- Five corrective actions were required at validation, including inaccurate sensitivity analysis in the IRR spreadsheet and a non-conservative annual electricity delivered value in the PDD
- The latest additionality tool was not applied for the common-practice analysis at the time of validation
- No verified ERR figure, FNRB value, or usage monitoring method is available in the extracted record
- Crediting period start date differs by 11 days between two monitoring reports (2013-01-01 vs 2012-12-21)
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2017 | 545,706 | 0 | 545,706 | |
| Total | 545,706 | 0 | 545,706 |
Risk Indicators
Combined test, VVB-verified
mixed evidence / unresolved risk
0% deduction, negligible for grid-displacing hydro
Jurisdictional grid EF, standard for hydro
Safeguards mentioned, benefit sharing described, but FPIC an
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →