8.5 MW wind power based electricity generation in the Northern and Western region grids of India
#103of 1935 in Renewable energy#53of 975 in India#58of 1459 in CDM (UNFCCC)#37of 806 in AMS-I.D
Audit Analysis
An 8.5 MW CDM wind project in India with a VVB-verified investment additionality test and a jurisdictional grid-emission-factor baseline. The project delivered roughly 100% of its pro-rata first-year expectation, but the PDD contained 20 material findings—including IRR calculation errors and an incorrect operating-margin emission-factor method—that were all subsequently resolved. Overall a competent but documentation-burdened project with no reversal risk and appropriate leakage treatment.
Red Flags
- Twenty material findings in the validation/monitoring record, including IRR calculation errors (tariff, depreciation, tax rates) and an operating-margin emission factor computed as a simple average rather than a generation-weighted average, both of which affected the additionality and baseline calculations before correction.
- The crediting-period start date (10 Nov 2010) preceded the CDM registration date, a compliance irregularity noted in the monitoring report.
- A discrepancy exists between the verified ERR of 14,327 tCO₂e recorded in the merged data and 12,152 tCO₂e cited in the monitoring report, a gap of roughly 15% that is unexplained in the available documents.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2014 | 12,506 | 0 | 12,506 | |
| Total | 12,506 | 0 | 12,506 |
Risk Indicators
VVB-confirmed investment test
Avoidance project, no reversal risk
Deemed negligible, appropriate for grid wind
Jurisdictional EF, OM calc error corrected
Mentioned, benefit sharing described, FPIC/grievance not sta
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →